Oklahoma Administrative Code
Title 785 - Oklahoma Water Resources Board
Chapter 35 - Well Driller and Pump Installer Licensing
Subchapter 11 - Plugging and Capping Requirements for Wells and Test Holes
Section 785:35-11-1 - Plugging and capping requirements for groundwater wells, fresh water observation wells, heat exchange wells and water well test holes
Current through Vol. 42, No. 1, September 16, 2024
(a) Temporary capping. When a groundwater well or fresh water observation well is temporarily removed from service, the top of the well casing will be properly sealed with a pitless adapter cap, sanitary well seal, or well casing cap that cannot easily be removed. A new well shall be properly capped before the well driller leaves the drilling site.
(b) Time for plugging or completing water well test holes. Water well test holes shall be properly plugged as provided in this section by the well driller prior to removal of drilling equipment unless the test hole is completed as an observation well for aquifer testing, including the installation of surface casing and cement seals. In the alternative and prior to drilling equipment being removed from site, water well test holes may be temporarily cased with SDR 26 water well casing a minimum of 10 feet below ground and 12 inches above ground. Bentonite shall be installed from 10 feet to 2 feet below land surface and cement grout installed from 2 feet to land surface. The top of casing shall be properly sealed or capped. Permanent completion or plugging shall become the responsibility of the landowner and shall be completed within 60 days of drilling equipment being removed from the site. A written statement from the landowner acknowledging such responsibility shall be obtained and submitted to the Board with the multipurpose completion report. The multi-purpose completion report shall be submitted to the Board within sixty (60) days after plugging or temporary completion of each water well test hole.
(c) Permanent abandonment. The following plugging requirements apply if a groundwater well, fresh water observation well, heat exchange well or water well test hole is permanently abandoned, was drilled by a person not holding a valid license or operator certification from the Board, or if the Board determines that the well or test hole was not drilled or completed in compliance with the applicable minimum standards set forth in this Chapter or may otherwise allow pollution to groundwater.
Amended at 10 Ok Reg 3299, eff 6-25-93 ; Amended at 11 Ok Reg 2947, eff 6-13-94 ; Amended at 12 Ok Reg 2703, eff 7-1-95 ; Amended at 15 Ok Reg 2440, eff 6-11-98 ; Amended at 16 Ok Reg 2686, eff 7-1-99 ; Amended at 22 Ok Reg 1598, eff 7-1-05 ; Amended at 25 Ok Reg 1444, eff 5-27-08 ; Amended at 30 Ok Reg 894, eff 6-13-13