(a) If, after any inspections, investigations, or examinations, or at any time after completion, it is found that amendments, modifications, or changes to the work performed pursuant to the approved plans and specifications are necessary to protect life and insure safety of the dam or to meet acceptable dam safety engineering practices, including those found in references set forth in 785:25-3-4, the owner shall be required to submit a revised application.

(b) If conditions are revealed which will not permit the construction of a safe dam or reservoir, the prior approval may be revoked or modified by the Board after notice and hearing.

(c) After the inspection, investigation, or examination, the Board shall, in a report to the owner, specify the deficiencies and allow a reasonable time for correcting the deficiencies.

Amended at 9 Ok Reg 1675, eff 5-11-92

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.