Section 730:10-1-4 - Eight Year Construction Work Plan balancing process
Current through Vol. 42, No. 1, September 16, 2024
(a) Project priorities among the individual Commission Districts shall be established in the context of the relative priorities for the systematic improvement of the highway system on a statewide basis.
(b) The development of Eight Year Construction Work Plan shall begin with the Field Division Engineers and will be guided by their knowledge of the transportation needs and priorities in their respective divisions. The Field Division Engineers and their staff shall work to maintain an understanding of the condition of the roads and bridges in their areas of responsibility. The general transportation system data and characteristics are considered to be fundamental considerations:
(c) This information shall be coupled with the careful consideration of the Field Division's condition and capacity assessments of the highway network and the associated critical needs, as well as, the anticipated improvement budgets and further communication with the Division's Transportation Commissioner.
(d) The Department is responsible for coordinating the State's transportation planning efforts with those of Oklahoma's Metropolitan Planning Organizations, substate planning districts and consulting with the tribal governments and local officials with responsibilities for transportation. The development of the Long Range Plan and the Statewide Transportation Improvement Plan as derived from the first four years of the Eight Year Construction Work Plan, Corridor Studies, as well as early project development all include opportunities for public participation and review. The results of this public involvement, input from ongoing coordination and consultation, and the planning documents shall be provided to the Field Division Engineers for their consideration during the development of the Eight Year Construction Work Plan.
(e) Project Schedules. The Department shall work to set realistic project delivery schedules, taking into account many variables, to maintain the integrity of the Eight Year Work Plan.
(f) Additional considerations.