Oklahoma Administrative Code
Title 460 - Department of Mines
Chapter 20 - The Permanent Regulations Governing the Coal Reclamation Act of 1979
Subchapter 43 - Permanent Program Performance Standards: Surface Mining Standards
Section 460:20-43-44 - Revegetation: timing
Current through Vol. 42, No. 1, September 16, 2024
(a) Disturbed areas shall be planted during the first normal period for favorable planting conditions after replacement of the plant-growth medium. The normal period for favorable planting is that planting time generally accepted locally for the type of plant materials selected.
(b) Vegetation that is in accordance with the approved permit and reclamation plan shall be established not more than 36 month after the disturbed areas have been retopsoiled, unless a written request for an extension has been submitted and approved by the Department prior to the expiration of the 36 month period.
(c) Extensions shall be approved solely on the basis of adverse climatic conditions demonstrated to the Department by the operator. Extensions shall be granted for no more than up to 12 months. Only one extension shall be approved.
Amended at 23 Ok Reg 3059, eff 7-27-06