Oklahoma Administrative Code
Title 460 - Department of Mines
Chapter 20 - The Permanent Regulations Governing the Coal Reclamation Act of 1979
Subchapter 31 - Underground Mining Permit Applications: Minimum Requirements for Reclamation
Section 460:20-31-22 - Interpretive rules related to general performance standards
Universal Citation: OK Admin Code 460:20-31-22
Current through Vol. 42, No. 1, September 16, 2024
The following interpretation of rules promulgated in Subchapter 31 of this Chapter have been adopted be the Department.
(1) Interpretation of Section 460:20-31-8: Reclamation plan: Postmining land uses.
(A)
The requirements of Section
460:20-31-8(a)(2)
of this Chapter, for approval of an alternative postmining land use, ma be met
by requesting approval through the permit revision procedures of Section
460:20-17-3 of
this Chapter rather than requesting such approval in the original permit
application. The original permit application, however, must demonstrate that
the land will be returned to its premining land use capability as required be
Section
460:20-45-51(a)
of this Chapter. An application for a permit revision of this type,
(i) must be submitted in accordance with the
filing deadlines of Section
460:20-17-3 of
this Chapter;
(ii) shall constitute
a significant alteration from the mining operation contemplated by the original
permit; and
(iii) shall be subject
to the requirements of Subchapters 15 and 19 of this Chapter.
Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.