Section 460:20-31-16 - Operation plan: maps and plans

Universal Citation: OK Admin Code 460:20-31-16

Current through Vol. 42, No. 1, September 16, 2024

Each application shall contain maps and plans as follows:

(1) The maps, plans, and cross sections shall show the underground mining activities to be conducted, the lands to be affected throughout the operation, and any change in a facility or feature to be caused by the proposed operations, if the facility or feature was shown under Sections 460:20-29-10 through 460:20-29-11 of this Chapter.

(2) The following shall be shown for the proposed permit area:

(A) Buildings, utility corridors, and facilities to be used;

(B) The area of land to be affected within the proposed permit area, according to the sequence of mining and reclamation;

(C) Each area of land for which a performance bond or other equivalent guarantee will be posted under Subchapter 37 of this Chapter;

(D) Each coal storage, cleaning, and loading area;

(E) Each topsoil, spoil, coal preparation waste, underground development waste, and noncoal waste storage area;

(F) Each water diversion, collection, conveyance, treatment, storage and discharge facility to be used;

(G) Each source of waste and each waste disposal facility relating to coal processing or pollution control;

(H) Each facility to be used to protect and enhance fish and wildlife related environmental values;

(I) Each explosives storage and handling facility;

(J) Location of each sedimentation pond, permanent water impoundment, coal processing waste bank, and coal processing water dam and embankment, in accordance with Section 460:20-31-9 of this Chapter and disposal areas for underground development waste and excess spoil, in accordance with Section 460:20-31-12 of this Chapter;

(K) Each profile, at cross sections specified by the Department, of the anticipated final surface configuration to be achieved for the affected areas;

(L) Location of each water and subsidence monitoring point; and

(M) Location of each facility that will remain on the proposed permit area as a permanent feature, after the completion of underground mining activities.

(3) Except as provided in Sections 460:20-31-9(a)(2), 460:20-31-9(a)(3), 460:20-31-12, 460:20-45-24(b), 460:20-45-26(c), 460:20-45-27(c) and 460:20-45-29(c) of this Chapter, cross sections, maps, and plans required under (2)(D), (E), (F), (J), and (K) of this Section shall be prepared by, or under the direction of, and certified by a qualified, registered, professional engineer, a professional geologist, or a qualified, registered, professional land surveyor, with assistance from experts in related fields such as landscape architecture.

Amended at 12 Ok Reg 3592, eff 10-12-95; Amended at 16 Ok Reg 3526, eff 9-13-99

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.