(a) Where a seismograph is used to monitor the velocity of ground motion and the peak particle velocity limit of 1 inch per second is not exceeded, the equation in Section 460:10-31-8(j) need not be used. If that equation is not used by the operator, a seismograph record shall be obtained for each shot.

(b) The use of a modified equation to determine maximum weight of explosives per delay for blasting operations at a particular site, may be approved by the Department, on receipt of a petition accompanied by reports including seismograph records of test blasting on the site. In no case shall the Department approve the use of a modified equation where the peak particle velocity of 1 inch per second required in Section 460:10-31-8(g) would be exceeded.

(c) The Department may require a seismograph record of any or all blasts and may specify the location at which such measurements are taken.

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.