Section 310:667-47-3 - Construction and inspection

Universal Citation: OK Admin Code 310:667-47-3

Current through Vol. 41, No. 13, March 15, 2024

(a) Construction other than minor alterations, shall not be commenced until Stage Two planreview deficiencies have been satisfactorily resolved.

(b) Prior to commencing construction, the contractor shall submit a construction schedule which includes, as a minimum, the start date, dates that the heating-ventilation air-conditioning (HVAC), plumbing, and medical gas installation shall commence, and projected date of completion.

(c) The completed construction shall comply with the approved drawings and specifications, including all addenda or modifications approved for the project.

(d) A final construction inspection of the facility shall be conducted by the Department for the purpose of verifying compliance with these requirements and the approved plans and specifications. The facility shall not allow patient occupancy until a final approval is granted by the Department.

Added at 12 Ok Reg 1555, eff 4-12-95 (emergency); Added at 12 Ok Reg 2429, eff 6-26-95

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.