Oklahoma Administrative Code
Title 310 - Oklahoma State Department of Health
Chapter 667 - Hospital Standards
Subchapter 47 - Submittal Requirements
Section 310:667-47-2 - Preparation of plans and specifications
Current through Vol. 41, No. 13, March 15, 2024
(a) Stage one. Preliminary plans and outline specifications shall be submitted and include sufficient information for approval by the Department of the following: scope of project; project location; required fire-safety and exiting criteria; building-construction type, compartmentation showing fire and smoke barriers, bed count and services; the assignment of all spaces, areas, and rooms for each floor level, including the basement. A hospital has the option, at its own risk, to bypass the stage one submittal and proceed directly to submittal of stage two documents. The option to bypass the stage one submittal does not apply if the project is being submitted for the stage two fast-track project review.
(b) Stage two. A proposed construction document shall be submitted that includes final drawings and specifications adequate for approval by the Department. All final plans and specifications shall be appropriately sealed and signed by an architect registered by the State of Oklahoma. All construction modifications of approved documents are subject to review and approval, and shall be submitted timely.
(c) Special submittals.
(d) Floor plan scale. Floor plans are to be submitted at a scale of one-eighth (1/8) inch equals one (1) foot, with additional clarifying documents as required.
(e) Application form. The submittal shall be made using a Department application form which requests information required by this Chapter and specifies the number of copies and format for document submittal.
Added at 12 Ok Reg 1555, eff 4-12-95 (emergency); Added at 12 Ok Reg 2429, eff 6-26-95