Oklahoma Administrative Code
Title 310 - Oklahoma State Department of Health
Chapter 663 - Continuum of Care and Assisted Living
Subchapter 7 - Physical Plant Design
Section 310:663-7-5 - Self-certification of plans
Current through Vol. 42, No. 1, September 16, 2024
(a) The Department shall make available consultation and technical assistance services covering the requirements of this section to an assisted living center considering self-certification of plans. The consultation and technical assistance is subject to the fees specified in OAC 310:663-7-3, The consultation is optional and not a prerequisite for filing a request through the self-certification review process.
(b) The assisted living center and the project architect or engineer may elect to request approval of design and construction plans through a self-certification review process. The assisted living center and the project architect or engineer submit a self-certification request on a form provided by the Department, along with the review fee specified in OAC 310:663-7-3. The form shall be signed by the assisted living center and the project architect or engineer attesting that the plans and specifications are based upon and comply with the requirements of this Chapter. The form shall require information necessary to demonstrate compliance with OAC 310:665-7-5(c).
(c) To be eligible for self-certification, projects must comply with the following requirements:
(d) Within twenty-one (21) calendar after receipt of a complete application, the Department shall approve or deny the application for self-certification and send notification to the assisted living center. If the application is denied, the assisted living center shall have thirty (30) calendar to submit additional or supplemental information demonstrating that the application complies with the requirements for self-certification of plans and specifications. The Department shall have fourteen (14) calendar after receipt of supplemental information to reconsider the initial denial and issue a final approval or denial of the self-certification request.
(e) After denial of the application for self-certification and prior to the start of construction, the assisted living center shall pay the applicable fee for plan review specified in OAC 310:663-7-3. Upon receipt of the plan review fee, the Department shall review the assisted living center's plans in accordance with the process in OAC 310:663-7-3.