Each utility shall make reasonable efforts to avoid interruption of service. When an interruption occurs service shall be re-established as soon as possible.

(1) Each utility shall keep a record of interruptions of service on its primary distribution system, including a statement of the time, duration and cause of each such interruption. The record shall be available to the Commission or its representative on request.

(2) The log for each unattended substation shall show interruptions that require attention to restore service with the estimated time and duration of interruption.

(3) Any planned interruption shall be made at a time that will not cause unreasonable inconvenience to consumers and shall be preceded by at least a two (2) day notice to consumers affected.

(4) The utility is required to report cyber security or infrastructure security events that affect customers immediately to the PUD Director or designee.

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.