(a) Upon written request to the Commission by a consumer, a test will be made of the consumer's meter by a representative of the Commission. The test shall be made as soon as reasonably possible after the request.

(b) The consumer may make written request to be present or have a representative present to witness the testing of the meter by a representative of the Commission. Upon receipt of such request, the Commission shall notify the utility to remove and seal the meter in the presence of the consumer and to keep the meter in the same condition with the seal unbroken until the test can be made in the presence of the consumer or his representative.

(c) Cost of the referee meter test shall be borne by the utility if the accuracy of the meter falls outside of the standards of the Commission. Cost of the test shall be borne by the consumer if the accuracy of the meter meets the standards of the Commission.

Amended at 16 Ok Reg 2380, eff 7-1-99

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.