Oklahoma Administrative Code
Title 165 - Corporation Commission
Chapter 45 - Gas Service Utilities
Subchapter 17 - Competitive Bidding and Affiliate Transaction Rules for the Provision of Natural Gas Services of Gas Supply, Gathering, Transmission and Storage of Natural Gas Utilities Upstream of the Citygate
Section 165:45-17-31 - Interconnection
Current through Vol. 41, No. 13, March 15, 2024
(a) In order to facilitate the Commission's policy to encourage new market entrants, upon the effective date of the rules of this Subchapter, each gas utility shall have the duty to provide for the interconnection of the facilities and equipment of any requesting pipeline with such utility's facilities:
(b) Although the Commission seeks to encourage new market entrants, new market entrants are strongly encouraged to bear the reasonable financial costs associated with interconnections. However, in no circumstances should the bid of the new market entrant be deemed inadequate due to the desire of the entrant to have the utility bear the cost for interconnection. In no event shall the utility seek recovery for the interconnection costs borne by the new market entrant.
(c) The requesting party shall reimburse the utility for all reasonable costs of an interconnection, unless the Commission, after notice and hearing, finds that it is in the best interests of the utilities' consumers for the utility to bear the cost of the interconnection.
(d) The utility may recover from its utility customers the costs involved with providing the interconnection which the Commission has determined, after notice and hearing, to be economically justified.
Added at 15 Ok Reg 2177, eff 7-1-98