Oklahoma Administrative Code
Title 158 - Construction Industries Board
Chapter 50 - Mechanical Industry Regulations
Subchapter 13 - Procedures of the Variance and Appeals Board, Plan Review Applications and Fees, Code Variance Applications and Fee, Code Interpretation Appeals
Section 158:50-13-1 - Plan review applications and fees
Current through Vol. 42, No. 1, September 16, 2024
(a) Applications for the review of plans and specifications to ensure conformance with State adopted installation codes may be submitted in writing to the Oklahoma Construction Industries Board. An application and the appropriate filing fee shall accompany the construction plans and specifications submitted for plan review. Plan review shall only be conducted for the construction projects where a city or town has not adopted a trade installation code by ordinance that is more stringent than the standard of installation as described in OAC 158:50-1-4. Applications shall only be reviewed by the Administrator if submitted prior to the bid dates for the project. Plan review shall be completed within (14) fourteen days of the receipt of a complete application.
(b) The Board will advise the applicant through its liaison if the application is determined to be incomplete in order for the applicant to re-submit a complete plan review application.
(c) The plan review fee for:
(d) Plan review is not required but is a service provided by the Board to assist with code compliance.
Added at 19 Ok Reg 732, eff 1-22-02 (emergency); Added at 19 Ok Reg 1276, eff 5-28-02