(A) Every frozen dessert manufacturer shall conduct, or have conducted for it, an analysis to determine whether there are food safety hazards that are reasonably likely to occur in conjunction with the manufacturing of frozen dessert and to identify the critical control points and preventive measures that apply to control those hazards. The analysis shall include food safety hazards which can occur both within and outside the processing plant environment, including food safety hazards that can occur before, during, and after processing. The frozen dessert manufacturers shall submit their analysis to the director.
(B) If the analysis done under paragraph (A) of this rule discloses that no food safety hazards are reasonably likely to occur, the frozen dessert manufacturer shall comply with rules 901:11-2-19 to 901:11-2-22, 901:11-2-25, 901:11-2-27 to 901:11-2-29, 901:11-2-33, 901:11-2-39, 901:11-2-40, 901:11-2-43 to 901:11-2-44 and 901:11-3-01 to 901:11-3-05 of the Administrative Code and shall be inspected at least once in a twelve month period by the director.
(C) If the analysis completed under paragraph (A) of this rule discloses one or more food safety hazards are reasonably likely to occur the frozen dessert manufacturer shall create and implement a HACCP plan.
(D) Signing and dating the HACCP plan.
(E) Every frozen dessert manufacturer required to create and implement a HACCP plan shall submit a copy of their HACCP plan to the director no later than three months after licensing.
(F) The director shall, within thirty days of receipt of the HACCP plan, either approve or disapprove the HACCP plan. The director shall disapprove the HACCP plan if it does not comply with the requirements of paragraphs (C) and (D) of this rule.
(G) If the director disapproves a HACCP plan he shall return the plan to the licensee with a statement of the changes necessary to bring the plan into compliance. The licensee shall have thirty days from its receipt of the plan to resubmit it to the director for reconsideration.
(H) The HACCP plan shall be implemented by the frozen dessert manufacturer within three months of notice of approval of the plan by the director. Prior to implementation of a HACCP plan, a frozen dessert manufacturer shall be inspected by the director and comply with the requirements listed in paragraph (B) of this rule.
(I) A licensed frozen dessert manufacturer shall be exempt from the requirements of this rule if he requests an exemption in writing and meets the criteria established in paragraphs (I)(1)(a) to (I)(1)(e) and (I)(2) of this rule.
(J) A frozen dessert manufacturer that meets the requirements of paragraphs (I)(1)(a) to (I)(1)(e) and (I) (2) of this rule shall be inspected at least once in a twelve month period by the director and shall comply with the requirements listed in paragraph (B) of this rule.