Ohio Administrative Code
Title 4906 - Power Siting Board
Chapter 4906-6 - Accelerated Certificate Applications
Section 4906-6-03 - Filing of an accelerated application
Current through all regulations passed and filed through September 16, 2024
(A) A letter of notification application shall be filed not less than ninety days before the planned commencement of construction. A letter of notification for which the applicant requests expedited processing shall be filed not less than twenty-eight days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-eight day requirement.
(B) A construction notice shall be filed not less than ninety days before planned commencement of construction. A construction notice for which the applicant requests expedited processing shall be filed not less than twenty-one days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-one day requirement.