Ohio Administrative Code
Title 4906 - Power Siting Board
Chapter 4906-6 - Accelerated Certificate Applications
Section 4906-6-03 - Filing of an accelerated application

Universal Citation: OH Admin Code 4906-6-03

Current through all regulations passed and filed through September 16, 2024

(A) A letter of notification application shall be filed not less than ninety days before the planned commencement of construction. A letter of notification for which the applicant requests expedited processing shall be filed not less than twenty-eight days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-eight day requirement.

(B) A construction notice shall be filed not less than ninety days before planned commencement of construction. A construction notice for which the applicant requests expedited processing shall be filed not less than twenty-one days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-one day requirement.

Disclaimer: These regulations may not be the most recent version. Ohio may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.