Ohio Administrative Code
Title 4901:1 - Utilities
Chapter 4901:1-43 - Recovery of Infrastructure Development Costs
Section 4901:1-43-04 - Cost recovery rider process
Current through all regulations passed and filed through September 16, 2024
(A) Each natural gas company's initial application for an infrastructure development rider pursuant to section 4929.161 of the Revised Code shall include all information set forth upon forms as may be prescribed by the commission.
(B) The commission may order that consultants be hired, with costs billed to the natural gas company, to conduct prudence and/or financial reviews of the costs incurred and recovered through the infrastructure development rider.
(C) Each annual report to update the infrastructure development rider should be made not less than seventy-five days prior to the proposed effective date of the updated rider rate. Proposed rates will become effective on the seventy-sixth day, unless suspended by the commission for good cause shown, and are subject to reconciliation adjustments following any hearing, if necessary.
(D) Affected parties may file a motion to intervene and submit comments on any issues within the following timelines: