(A) Level 3 review qualifying criteria
In order for the application to be approved by the EDU under the level 3 review procedure, one of the following conditions must apply:
(1) The DER does not qualify or
failed to meet the level 1 or level 2 interconnection review
requirements.
(2) The DER does not
utilize equipment that is certified in compliance with the IEEE and UL
standards as set forth in rule
4901:1-22-03 of the
Administrative Code.
(3) The DER
has a nominal nameplate capacity of twenty megawatts or less.
(B) Level 3 approval criteria
(1) Level 3 review procedure
uses the determinations made in the scoping meeting
and any feasibility, system impact, or facilities study defined in rule
4901:1-22-09 of the
Administrative Code for technical analysis of the applicant's proposed DER
installation.
(2) The EDU shall
approve an application for interconnection under level 3 review procedures if
the EDU determines that the safety and reliability of the public utility's
transmission or distribution system will not be compromised by interconnecting
with the generation facility.
(C) Level 3 fees
(1) The EDU's tariff for level 3 review fees
will include the following:
(a) An application
fee of up to one hundred dollars, plus two dollars per kilowatt of the system's
nominal nameplate capacity.
(b) The
cost of engineering work done as part of any feasibility, system impact or
facilities study, billed at actual cost.
(c) The actual cost of any modifications of
the EDU's system that would otherwise not be done but for the applicant's
interconnection request.
(2) Within five business days after
completion of the level 3 review including any applicable feasibility, system
impact or facilities studies leading to the EDU's approval for interconnection
of the applicant's proposed DER installation and collection by the EDU of all
the actual costs for the studies as billed to the applicant, the EDU shall
provide the applicant with a standard interconnection agreement.
Disclaimer: These regulations may not be the most recent version. Ohio may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.