Ohio Administrative Code
Title 4901:1 - Utilities
Chapter 4901:1-22 - Interconnection Services
Section 4901:1-22-07 - Level 2 review procedure
Current through all regulations passed and filed through September 16, 2024
(A) Level 2 qualifying criteria
In order for the application to be reviewed by the EDU under the level 2 review procedure, the applicant's DER must meet the following requirements:
Line Voltage |
Nominal Nameplate Capacity |
Nominal Nameplate Capacity if located on a 600 amp line and within 2.5 feeder miles of substation |
less than or equal to 5kV |
less than or equal to 500 kW |
less than 2 MW |
5kV less than or equal to 15 kV |
less than or equal to 2MW |
less than 3 MW |
15 kV less than or equal to 30 kV |
less than or equal to 3MW |
less than 4 MW |
30 kV less than or equal to 69 kV |
less than or equal to 4MW |
less than 5 MW |
(B) Level 2 approval criteria
Primary Distribution Line Configuration |
Interconnection to Primary Distribution Line |
Three phase, three wire |
If a three-phase or single-phase DER, interconnection must be phase-to-phase |
Three phase, four wire |
If a three-phase (effectively grounded) or single phase DER, interconnection must be line-to-neutral |
(C) Level 2 review timeframe
(D) Facility or minor system modifications
(E) Level 2 supplemental review
(F) Level 2 fees
The EDU's tariff for level 2 review processing fees will include the following: