Ohio Administrative Code
Title 4123:1 - Division of Safety and Hygiene
Chapter 4123:1-5 - Workshops and Factories
Section 4123:1-5-26 - Trenches and excavations
Universal Citation: OH Admin Code 4123:1-5-26
Current through all regulations passed and filed through September 16, 2024
(A) General specifications.
(1)
Utility companies and municipally owned utilities will be
contacted and advised of proposed work prior to the start of actual excavation.
Prior to opening an excavation, effort will be made to
determine whether underground installations, i.e., sewer, telephone, water,
fuel, electric lines, etc., will be encountered and, if so, where such
underground installations are located.
(2) An employee will not be
required to use mechanical digging or trenching equipment within three feet of
an energized underground electrical conductor whose location is known, unless
the conductors are protected by concrete ducts or equivalent
protection.
(3) Where trenches or
excavations are made in locations adjacent to backfilled trenches or
excavations or where trenches or excavations are subjected to vibrations from
any source, such as railroad or highway traffic or the operation of machinery,
additional precautions by way of shoring and bracing will be taken to
prevent slides or cave-ins.
(4)
Undercutting of the exposed faces of trenches or excavations is
not
permitted unless the exposed faces of such undercutting are supported by
one or more of the methods prescribed for the support of exposed faces of
trenches.
(5) Material placement.
(a) Excavated material or other material
will be
retained a minimum of twenty-four inches from the top edge of the trench or
excavation.
(b) As an alternative
to the clearance prescribed in paragraph (A)(5)(a) of this rule, the employer
will use
effective barriers or other effective retaining devices in lieu thereof in
order to prevent excavated or other materials from falling into the trench or
excavation.
(6) Wells,
pits, shafts etc.
(a) All wells, pits, shafts,
etc., will be barricaded or covered.
(b) Upon completion of exploration and
similar operations, temporary wells, pits, shafts, etc.,
will be
backfilled.
(B) Trenches.
(1) The exposed faces of all
trenches more than five feet high
will be shored, laid back to a stable slope, or
some other equivalent means of protection
will be
provided where employees may be exposed to moving ground or caveins. (See table
26-1 to this rule.)
(2) Sides of
trenches in unstable or soft material, five feet or more in depth,
will be
shored, sheeted, braced, sloped, or otherwise supported by means of sufficient
strength to protect the employees working within them. (See table 26-1 and
table 26-2 to this rule.)
(3) Sides
of trenches in hard compact soil, including embankments,
will be
shored or otherwise supported when the trench is more than five feet in depth
and eight feet or more in length. In lieu of shoring, the sides of the trench
above the five-foot level may be sloped to preclude collapse, but
will
not be steeper than a one-foot rise to each one-half-foot horizontal.
(4) Materials used for sheeting and sheet
piling, bracing, shoring, and underpinning, will be in good
serviceable condition, and timbers used will be sound
and free from large or loose knots, and will be designed
and installed so as to be effective to the bottom of the trench.
(5) Minimum specifications - trench shoring.
(a) Minimum specifications for trench bracing and shoring
will be
in accordance with table 26-2 to this rule. The vertical planks in the bracing
system will extend at least to the top of the trench
face.
(b) Braces and diagonal
shores in a wood shoring system will not be subjected to compressive stress in excess
of values given by the following formula:
S = 1300 - 20L ÷ D
Maximum ratio: L ÷ D = 50
Where: L = length, unsupported, in inches.
D = least side of the timber in inches.
S = allowable stress in pounds per square inch of cross section.
(6) When
employees are working in trenches four feet deep or more, an
adequate means of exit, such as a ladder or steps, will be provided
and located so as to require no more than twenty-five feet of lateral
travel.
(7) When bracing or shoring
of trenches is needed, such bracing and shoring
will be
carried along with the excavation.
(8) Cross braces or trench jacks
will be
placed in true horizontal position, be spaced vertically, and be secured to
prevent sliding, falling, or kickouts.
(9) Portable trench boxes, safety cages or
sliding trench shields may be used for the protection of employees in lieu of a
shoring system or sloping. Where such trench boxes or shields are used, they
will be
designed, constructed, and maintained in a manner which will provide protection
equal to or greater than the sheeting or shoring needed for
the trench and will extend at least to the top of the trench
face.
(10) Backfilling and removal
of trench supports will progress together from the bottom of the trench.
Jacks or braces will be released slowly, and, in unstable soil,
employees will clear the trench before pulling out the jacks or
braces with ropes.
(C) Excavations.
(1) The walls and faces of all
excavations in which employees are exposed to danger from moving ground
will be
guarded by a shoring system, sloping of the ground, or some other equivalent
means. (See table 26-1 and table 26-2 to this rule.)
Table 26-1.
(2)
Supporting systems, i.e., piling, cribbing, shoring etc., shall be designed by
a qualified person and shall meet accepted engineering
specifications.
(3) Excavations sloped to the angle of repose
will be
flattened when an excavation has water conditions, silty materials, loose
boulders, and areas where erosion, deep frost action, and slide planes
appear.
(4) Sides, slopes, and
faces of all excavations will meet accepted engineering
specifications by scaling, benching, barricading, rock
bolting, wire meshing, or equally effective means.
(5) Materials used for sheeting, sheet
piling, cribbing, bracing, shoring, and underpinning will be in good
serviceable condition, and timbers will be sound,
free from large or loose knots, and of proper dimensions. (See table 26-2 to
this rule for proper dimensions.)
(6) Excavations below the level of the base
of the footing of any foundation or retaining wall are
not
permitted, except in hard rock, unless the wall is underpinned and
appropriate precautions are taken to ensure the stability of adjacent
walls.
(7) If it is necessary to
place or operate power shovels, derricks, trucks, materials, or other heavy
objects on a level above and near an excavation, the side of the excavation
will be
sheet-piled, shored, braced or sloped as necessary to resist the extra pressure
due to such super-imposed loads.
(8) When mobile equipment is utilized or
allowed adjacent to excavations, substantial stop logs or barricades
will be
installed.
(9) Where employees or
equipment cross over
excavations, walkways or bridges with standard guardrails
will be
provided.
Disclaimer: These regulations may not be the most recent version. Ohio may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.