Ohio Administrative Code
Title 3745 - Ohio Environmental Protection Agency
Chapter 3745-580 - Scrap tire
Section 3745-580-22 - Closure cost estimate, post closure care cost estimate, and financial assurance for scrap tire facilities and scrap tire transporters
Current through all regulations passed and filed through September 16, 2024
For the purposes of this rule, "owner or operator" means the owner or operator of a scrap tire transportation business, the owner or operator of a scrap tire storage facility, the owner or operator of a scrap tire recovery facility, the owner or operator of a mobile scrap tire recovery facility, the owner or operator of a scrap tire monocell, or the owner or operator of a scrap tire monofill.
[Comment: Financial assurance information is submitted as part of a permit to install or registration certificate application for a new scrap tire facility, a modification that increases the closure cost estimate of an existing scrap tire facility, a modification that increases the post-closure care cost estimate of an existing scrap tire facility, or an alteration to a scrap tire facility that changes the amount of scrap tires or scrap tire product stored. For a scrap tire transporter, financial assurance information is executed and funded as part of an initial registration certificate application.]
(A) Exclusions. The owner or operator of the following scrap tire facilities are excluded from the requirements of this rule:
(B) Closure cost estimate. The owner or operator shall prepare a closure cost estimate in accordance with the following criteria:
(C) Post-closure care cost estimate for a scrap tire monofill facility. The owner or operator of a scrap tire monofill facility shall prepare a written post-closure care cost estimate in current dollars, identifying the cost for a third party to conduct post-closure care.
(D) Closure cost estimate review. The owner or operator of a scrap tire facility shall review and make appropriate revisions to the closure cost estimate as follows:
(E) Post-closure care cost estimate review. The owner or operator of a scrap tire monofill facility shall review and make appropriate revisions to the post-closure care cost estimate as follows:
(F) Whenever a revision performed as specified in paragraph (D) or (E) of this rule results in an increase to the closure cost estimate or post-closure care cost estimate, the owner or operator shall ensure the financial assurance instrument is increased in accordance with rule 3745-503-05 or 3745-503-10 of the Administrative Code, as applicable.
(G) The owner or operator of a scrap tire storage facility or scrap tire recovery facility may request a reduction in the financial assurance if the owner or operator reduces the size of the scrap tire storage areas.
(H) The owner or operator shall ensure financial assurance instruments account for increases in the closure cost estimate and that sufficient financial assurance is available for closure activities at all times during the operating life of the scrap tire facility and until the facility is certified closed.
(I) For a scrap tire monofill facility, the owner or operator shall ensure financial assurance instruments account for increases in the post-closure care cost estimate and that sufficient financial assurance is available at all times during the post-closure care period, until the post-closure care period ends.
(J) The director may require revisions to the closure cost estimate, post-closure care cost estimate, or financial assurance instrument if the director determines that the cost of closure or post-closure care exceeds the cost estimate or the amount of the financial assurance instrument.
(K) Paragraph (B)(1) or (B)(4) of this rule is not applicable to the owner or operator if the closure cost estimate is five thousand five hundred dollars or less.