Ohio Administrative Code
Title 3745 - Ohio Environmental Protection Agency
Chapter 3745-57 - Disposal of Hazardous Waste in Landfills
Section 3745-57-81 - Assessment of existing drip pad integrity

Universal Citation: OH Admin Code 3745-57-81

Current through all regulations passed and filed through September 16, 2024

(A) For each existing drip pad as identified in rule 3745-57-80 of the Administrative Code, the owner or operatormust evaluate the drip pad and determine whether it meets all of the requirements of rules 3745-57-80 to 3745-57-85 of the Administrative Code, except the requirements for liners and leak detection systems of paragraph (B) of rule 3745-57-83 of the Administrative Code. No later thanSeptember 2, 1997, the owner or operator must obtain and keep on file at the facility a written assessment of the drip pad, reviewed and certified by a qualified professional engineer that attests to the results of the evaluation. The assessment must be reviewed, updated and re-certified annually until all upgrades, repairs, or modifications necessary to achieve compliance with all of the standards of rule 3745-57-83 of the Administrative Code are complete. The evaluationmust document the extent to which the drip pad meets each of the design and operating standards of rule 3745-57-83 of the Administrative Code are complete. The evaluation shall document the extent to which the drip pad meets each of the design and operating standards of rule 3745-57-83 of the Administrative Code, except the standards for liners and leak detection systems, specified in paragraph (B) of rule 3745-57-83 of the Administrative Code.

(B) The owner or operator must develop a written plan for upgrading, repairing, and modifying the drip pad to meet the requirements of paragraph (B) of rule 3745-57-83 of the Administrative Code, and submit the plan to the director no later than two years before the date that all repairs, upgrades, and modifications will be complete. This written planmust describe all changes to be made to the drip pad in sufficient detail to document compliance with all the requirements of rule 3745-57-83 of the Administrative Code. The planmust be reviewed and certified by a qualified professional engineer.

(C) Upon completion of all upgrades, repairs, and modifications, the owner or operator shall submit to the director the as-built drawings for the drip pad together with a certification by an independent qualified registered professional engineer attesting that the drip pad conforms to the drawings.

(D) If the drip pad is found to be leaking or unfit for use, the owner or operator must comply with the provisions of paragraph (M) of rule 3745-57-83 of the Administrative Code or close the drip pad in accordance with rule 3745-57-85 of the Administrative Code.

Disclaimer: These regulations may not be the most recent version. Ohio may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.