(A) Facility design and construction. The composting facility shall be designed and constructed to meet the following:
"This composting facility only accepts yard waste and agricultural plant materials and will not accept hazardous wastes, infectious wastes, asbestos, batteries, or other prohibited materials."
(B) Site preparation. The following requirements shall be completed prior to initial acceptance of feedstocks, bulking agents, or additives at the composting facility:
(C) Initial acceptance of feedstocks. The owner or operator may begin to accept feedstocks, bulking agents, or additives if the owner or operator has submitted a registration application that complies with paragraphs (A) and (B) of rule 3745-560-401 of the Administrative Code, the owner or operator has complied with paragraphs (A) and (B) of this rule, and one of the following occurs:
(D) Notwithstanding the provisions of paragraph (C) of this rule, the owner or operator shall not begin to accept feedstocks, bulking agents, or additives if not later than ninety days after Ohio EPA received the registration application, the director has provided a written notification of deficiency to the owner or operator that the registration application does not comply with paragraphs (A) and (B) of rule 3745-560-401 of the Administrative Code or that the owner or operator has not complied with paragraphs (A) and (B) of this rule. If the owner or operator fails to address the deficiencies, the director may deny the registration application or approve the registration application with a variance or exemption.