Ohio Administrative Code
Title 3745 - Ohio Environmental Protection Agency
Chapter 3745-512 - Construction
Section 3745-512-17 - Alternative construction materials evaluation and reporting
Current through all regulations passed and filed through December 16, 2024
[Comment: For dates of non-regulatory government publications, publications of recognized organizations and associations, test methods, federal rules, and federal statutory provisions referenced in this rule, see rule 3745-500-03 of the Administrative Code titled "Incorporation by reference."]
(A) Upon approval by the permitting authority, the owner or operator may use an alternative construction material if the alternative construction material undergoes an evaluation in accordance with this rule prior to use to construct the facility.
[Comment: This rule requires approval prior to use of the alternative construction material; therefore, a construction certification report cannot include a request for approval of an alternative construction material.] [Comment: As defined and instructed by the applicable program chapter, if use of the alternative construction material meets the definition of an alteration, the owner or operator shall also submit an alteration request (the alternative construction material evaluation may be included in the alteration request). If use of the alternative construction material meets the definition of a modification, the owner or operator shall also submit a permit to install application (the alternative construction material evaluation may be included in the permit to install application).]
(B) The alternative construction material evaluation shall be signed and sealed by a professional engineer and include the following:
(C) The approval for use of an alternative construction material is valid only for the area identified in the alternative construction material request. If the alternative construction material is to be used in additional areas, the owner or operator shall submit another evaluation under this rule.
(D) Approval to use an alternative construction material does not relieve the owner or operator from complying with requirements established by this chapter and any specification in the authorizing document.
(E) The permitting authority shall not approve use of an alternative construction material unless the permitting authority determines the following: