Ohio Administrative Code
Title 3745 - Ohio Environmental Protection Agency
Chapter 3745-31 - Permit-to-Install New Sources and Permit-to-Install and Operate Program
Section 3745-31-02 - Applicability, requirements, and obligations
Current through all regulations passed and filed through December 16, 2024
[Comment: For dates and availability of non-regulatory government publications, publications of recognized organizations and associations, federal rules, and federal statutory provisions referenced in this rule, see paragraph (AA) of rule 3745-31-01 of the Administrative Code titled, "referenced materials."]
This chapter provides requirements for installation, modification and operation of new and existing air contaminant sources at facilities that are not subject to Chapter 3745-77 of the Administrative Code. This chapter also provides requirements for installation and modification of air contaminant sources at facilities that are, or will be, subject to Chapter 3745-77 of the Administrative Code. The operating requirements for air contaminant sources, defined as Title V sources, can be found in Chapter 3745-77 of the Administrative Code.
[Comment: Prior to June 30, 2008, requirements for permits-to-operate for sources not subject to Chapter 3745-77 of the Administrative Code were contained in Chapter 3745-35 of the Administrative Code. On June 30, 2008, Chapter 3745-35 was rescinded and all operating requirements for sources at facilities not subject to Chapter 3745-77 of the Administrative Code were incorporated into this chapter. Rules 3745-31-01 to 3745-31-07 of the Administrative Code provide regulatory requirements for installation and modification for all sources. Rules 3745-31-01 to 3745-31-07 of the Administrative Code also provide regulatory requirements for operation of sources at facilities not subject to Chapter 3745-77 of the Administrative Code. Rule 3745-31-08 of the Administrative Code provides the on-going regulatory requirements for sources at facilities not subject to Chapter 3745-77 of the Administrative Code that previously received registration status for permit-to-operate purposes under the now rescinded Chapter 3745-35 of the Administrative Code. Updated requirements for registration status, now defined as express permit-to-install or express PTIOs, are incorporated into rule 3745-31-05 of the Administrative Code. Rule 3745-31-09 of the Administrative Code provides for operation or other use of an air contaminant source that emits any air pollutant under a variance. This provision was previously established in the now rescinded rule 3745-35-03 of the Administrative Code. Rule 3745-31-29 of the Administrative Code provides for general permits-to-install and general PTIOs. Rule 3745-31-33 of the Administrative Code identifies activities that are included or excluded from the meaning of begin actual construction, as defined in rule 3745-31-01 of the Administrative Code. The remaining rules in this chapter, rules 3745-31-10 to 3745-31-28 and rule 3745-31-32 of the Administrative Code, provide additional regulatory requirements for installation and modification of air contaminant sources that are located at a major stationary source or are considered major modifications, as defined in rule 3745-31-01 of the Administrative Code. Installation or modification of air contaminant sources that are located at a major stationary source or are considered major modifications, are, or will become, subject to Chapter 3745-77 of the Administrative Code.
The operating regulatory requirements for these types of sources are contained in Chapter 3745-77 of the Administrative Code.]
[Comment: Prior to the effective date of this rule, permits-by-rule were contained in rule 3745-31-03 of the Administrative Code. The permits-by-rule have been moved to rule 3745-31-30 of the Administrative Code.]
(A) Permit-to-install or PTIO
[Comment: Paragraph (A)(1)(b) of this rule is not intended to prohibit any new source, as defined in rule 3745-31-01 of the Administrative Code, currently operating under an effective permit-to-install or permit-to-operate from continuing operation in accordance with those permits. Nor is it intended to prohibit any new source currently operating under an expired permit-to-operate, where a timely and complete application for renewal is pending in accordance with division (C) of section 119.06 of the Revised Code, from continuing operation in accordance with the expired permit-to-operate until such time as a new PTIO is issued or denied.]
(B) Changes in applicability: Title V versus non-Title V.
This paragraph is applicable to an owner or operator where a change in the air contaminant source, stationary source, or applicable law results in a change in the requirements applicable to the source under this chapter or Chapter 3745-77 of the Administrative Code. A change may include, but is not limited to, a modification or major modification as defined in this chapter, a relaxation of a federally enforceable limitation on the potential to emit applicable under paragraph (D) of rule 3745-31-05 of the Administrative Code, or the imposition of a federally enforceable limitation, or limitation legally and practicably enforceable by the state, on the potential to emit that restricts a stationary source's potential to emit below major source thresholds applicable under paragraph (D) of rule 3745-31-05 of the Administrative Code.
[Comment: An owner or operator with authority to operate under a Title V permit which subsequently makes a change at the facility that eliminates the applicability of Chapter 3745-77 of the Administrative Code is not obligated to obtain a PTIO or FEPTIO if the owner or operator elects to continue to be permitted under the Title V permit.]
V permit, except as expressly released in rule, by order of the director, or a in a federally enforceable permit.
(C) Permanent shutdown of an air contaminant source subject to the terms and conditions of a permit-to-install or PTIO.
When expressly provided in the terms and conditions of a permit-to-install or PTIO, the owner or operator of an air contaminant source that is permanently shutdown may be relieved from certain requirements in the terms and conditions of the permit-to-install or PTIO, without obtaining a modification or administrative modification, upon meeting the requirements specified in the permit for permanently shutting down air contaminant sources. Those terms and conditions for which the owner or operator is relieved will cease to be enforceable upon meeting the requirements for permanently shutting down air contaminant sources contained in the terms and conditions of the permit.
(D) The director, in the director's discretion, may issue an order requiring any person planning to install or modify, or in the process of installing or modifying, any air contaminant source as defined in rule 3745-31-01 of the Administrative Code, that is otherwise exempted, to obtain a permit-to-install or PTIO, before proceeding with installation or modification, if in the director's judgment, operation of the air contaminant source after installation or modification might result in a violation of the criteria established in paragraph (A) of rule 3745-31-05 of the Administrative Code.
(E) The director, in the director's discretion or where required to do so by federal laws or regulations, may issue a single permit-to-install or PTIO having application to all pollutants of any kind emanating from any air contaminant source, or issue a single permit-to-install or PTIO having applicability to more than one air contaminant source, controlled by a common owner or operator, located in the same county.
(F) The approval to construct or operate under this chapter shall not relieve any owner or operator of a stationary source of the responsibility to comply fully with applicable provisions of this chapter and any other requirements under local, state or federal law.
(G) If any provision of this chapter or the application of such provision to any person or circumstance, is held invalid, the remainder of this chapter, or the application of such provision to persons or circumstances other than those as to which it is held invalid, shall not be affected thereby.