(A) Each owner or
operator to whom this rule applies shall perform the following:
(1) Provide the director a notice of
intention to demolish or renovate on a form and in manner prescribed by the
director.
(2) Update notice, as
necessary, including when the amount of asbestos affected changes by at least
twenty per cent.
(3) Notify the
director via one of the following schedules:
(a) At least ten working days before the
beginning of any demolition operation, asbestos stripping or removal work, or
any other activity including salvage activities and preparations that break up,
dislodge or similarly disturb asbestos material if the operation is a
demolition or renovation operation subject to this rule.
(b) At least ten working days before the end
of the calendar year preceding the year for which notice is being given for
individual nonscheduled renovations described in paragraph (B)(4)(a) of rule
3745-20-02 of the Administrative
Code.
(c) As early as possible
before, but not later than, the following working day if the operation is an
emergency demolition, or if the operation is an emergency renovation.
(d) For asbestos stripping or removal work in
any subject demolition or renovation operation (except for any nonscheduled
renovation operations, emergency renovation operations and emergency demolition
operations) that will begin on a date other than the one contained in the
original notice, provide notice of the new start
date to the director as
follows:
(i) When the asbestos stripping or
removal operation or demolition operation covered by this paragraph will begin
after the date contained in the notice:
(a)
Notify the Ohio EPA field office of the new start date by telephone as soon as
possible before the original start date.
(b) Notify the director of the new start date
as soon as possible before, and no later than, the original start date. Deliver
amended notice on a form and in a manner prescribed by the director.
(ii) When the asbestos stripping
or removal operation or demolition operation covered by this paragraph will
begin on a date earlier than the original start date:
(a) Notify the director of the new start date
at least ten working days before asbestos stripping or removal work
begins.
(b) For demolition covered
by paragraph (B)(2) of rule
3745-20-02 of the Administrative
Code, notify the director of a new start date at least ten working days before
commencement of demolition. Deliver an amended notice on a form and in a manner
prescribed by the director.
(iii) In no event shall an operation covered
by this paragraph begin on a date other than the date contained in the notice
of the new start date.
(4) The owner or operator shall include the
following information in the notice:
(a) An
indication of whether the notice is the original or a revised
notification.
(b) Name, address,
and telephone number of the facility owner and of the facility
operator.
(c) Name, address,
telephone number, and Ohio asbestos hazard abatement contractor license number
(if applicable) of the asbestos demolition or renovation operator.
(d) Location and street address (including
building number or name and floor or room number, if appropriate), city,
county, and state of the facility being demolished or renovated. Attach to the
notification, any site plans, floor plans or other information that may be
necessary to enable the operations to be located for inspection.
(e) Type of operation: demolition or
renovation.
(f) Description of the
facility or affected part of the facility including the size (square feet, and
number of floors), age, and present and prior use of the facility.
(g) Estimate of the amount of regulated
asbestos-containing material to be removed from the facility in terms of length
of pipe in linear feet, surface area in square feet on other facility
components, or volume in cubic feet where the length or area cannot be
measured. Also, estimate the approximate amount of category I and category II
nonfriable asbestos- containing material in the affected part of the facility
that will not be removed before demolition.
(h) Description of the procedures, including
analytical methods, employed to detect the presence of and to estimate the
quantity of regulated asbestos- containing material and category I and category
II nonfriable asbestos- containing material in the facility.
(i) Scheduled starting and completion dates
of asbestos removal work or any other activity, such as site preparation that
would break up, dislodge, or similarly disturb asbestos material in the
demolition or renovation; planned renovation operations involving individual
nonscheduled operations shall only include the beginning and ending dates of
the report period as described in paragraph (B)(4)(a) of rule
3745-20-02 of the Administrative
Code.
(j) Description of the
planned demolition or renovation work to be performed and methods to be
employed including demolition or renovation techniques to be used and a
description of affected facility components.
(k) Description of work practices and
engineering controls to be used to comply with the requirements of this
chapter, including asbestos removal and waste handling emission control
procedures.
(l) Name and location of
the waste disposal site where the asbestos-containing waste material will be
deposited.
(m) Scheduled starting
and completion dates of demolition or renovation.
(n) Description of procedures to be followed
in the event that unexpected regulated asbestos-containing material is found or
nonfriable asbestos- containing material becomes crumbled, pulverized, or
reduced to powder.
(o) Name,
address, and telephone number of the waste transporter.
(p) A certification that at least one person
trained as required by paragraph (B) of rule
3745-20-04 of the Administrative
Code will supervise the stripping and removal described by this
notification.