Current through all regulations passed and filed through December 16, 2024
[Comment: For dates of non-regulatory
government publications, publications of recognized organizations and
associations, federal rules, and federal statutory provisions referenced in
this rule, see paragraph (C) of rule 3745-107-01 of the Administrative
Code.]
(A)
Final compliance timelines for the standards of
performance and associated monitoring record keeping and reporting shall be as
follows:
(1)
For an owner or operator of an EGU subject to this chapter before the effective
date of this rule, no later than July 8, 2024.
(2)
For an owner or
operator of an EGU subject to this chapter that no longer meets an exclusion
under
40 CFR
60.5780a, no more than twenty-four months
from Ohio's revised plan submittal required under 40 CFR part 60, subpart
UUUUa.
(3)
In lieu of the compliance schedule in paragraph (A)(1)
or paragraph (A)(2) of this rule, an extended compliance schedule may be
approved by the director provided there are legally enforceable increments of
progress to achieve compliance for each EGU. Where practicable, increments of
progress shall include the following:
(a)
Submittal of a
final control plan for the EGU to the director.
(b)
Awarding of
contracts for emission control systems or for process modifications, or
issuance of orders for the purchase of component parts to accomplish emission
control or process modification.
(c)
Initiation of
on-site construction or installation of emission control equipment or process
change.
(d)
Completion of on-site construction or installation of
emission control equipment or process change.
(B)
EGU-specific
operational characteristics, heat rate study and standard of performance
proposals required under rule 3745-107-02 of the Administrative Code shall be
submitted as follows:
(1)
For an owner or operator of an EGU subject to this
chapter before the effective date of this rule, no later than May 3,
2021.
(2)
For an owner or operator of an EGU that no longer meets
an exclusion under
40 CFR
60.5780a, no later than one hundred twenty
days after becoming subject to this chapter.
(C)
The director
shall make the standard of performance and associated monitoring, record
keeping and reporting enforceable by adopting in the Ohio Administrative Code;
issuing in a permit under either Chapter 3745-77 or Chapter 3745-31 of the
Administrative Code; by director's order; or by an Ohio consent agreement,
according to the following:
(1)
For an owner or operator of an EGU subject to this
chapter before the effective date of this rule, prior to the plan due date for
Ohio's plan required under 40 CFR part 60, subpart UUUUa.
(2)
For an owner or
operator of an EGU that no longer meets an exclusion under
40 CFR
60.5780a, prior to submittal of Ohio's
revised plan required under 40 CFR part 60, subpart
UUUUa.