Section 3737-1-12.1 - Mandatory and voluntary pre-approval of corrective action costs
Current through all regulations passed and filed through September 16, 2024
(A) For corrective actions to be performed in accordance with all versions of rule 1301:7-9-13 of the Administrative Code, the responsible person shall submit to the director an application for initial pre-approval of costs for pending corrective actions, as follows:
(B) Where estimated cost and completion schedules have been pre-approved in accordance with paragraphs (A)(2), (A)(6), and (A)(7) of this rule, the responsible person shall submit pre-approval applications annually, unless otherwise determined by the director, on a form prescribed by the director.
(C) Upon receipt of a pre-approval application submitted pursuant to this rule, the director shall evaluate the estimated cost and completion schedule. In evaluating the estimated cost and completion schedule to be pre-approved, the director shall consider what is usual, customary and reasonable for similar corrective action activities and under similar circumstances as determined from the fund's experience. At the director's discretion, other options including, but not limited to, pay-for-performance or risk sharing by the consultant and the responsible person may be considered for the corrective actions for which pre-approval is sought. The director shall notify the responsible person of the pre-approved costs and completion schedule.
(D) The responsible person shall immediately notify the director and submit a revised estimated cost and completion schedule for pre-approval as follows:
(E) Where a revised estimated cost and completion schedule is submitted for pre-approval, the director may review the estimated cost and completion schedule in accordance with paragraph (C) of this rule or provide notification to the responsible person that the estimated cost and completion schedule will be evaluated when the application for reimbursement is submitted to the board in accordance with rule 3737-1-12 of the Administrative Code.
(F) Where an estimated cost and completion schedule is required by this rule, estimated costs shall be detailed on a time and material basis.
(G) Corrective action costs and completion schedules not submitted for pre-approval in accordance with this rule shall be evaluated for reimbursement and subject to reductions in reimbursement in accordance with rule 3737-1-09 of the Administrative Code.
(H) Where pre-approval is not required by this rule but is desired by the responsible person, the responsible person may submit to the director a description of the proposed corrective actions and an estimated cost and completion schedule for pre-approval.
(I) Pre-approval shall not accelerate fund reimbursement for a release. Payment for pre-approved costs shall be contingent upon the proper submission of an application for reimbursement in accordance with rule 3737-1-12 of the Administrative Code, and a determination that a responsible person is eligible to receive reimbursement from the fund.