Current through all regulations passed and filed through September 16, 2024
(A)
The low pressure
distribution design shall include the entire network configuration including,
but not limited to, pipe lengths and size, exterior control panel and alarm
information, and calculations used to determine dose volume, orifice flow
rates, dosing tank sizing and pump selection within the following
specifications:
(1)
Distribution network
(a)
Supply network
piping including the main, sub-mains, and manifold shall be watertight, rigid
solid wall pipe, and shall be properly supported to prevent sagging and damage
under normal loads and operating conditions. All network piping and low
pressure distribution piping and fittings shall be polyvinyl chloride meeting
ASTM Standard D 1785 Schedule 40, 80, or 120 or ASTM D 2241, SDR 13.5, 17, or
21 or equivalent. All fittings shall be pressure rated meeting or exceeding
ASTM D 2466.
(b)
Manifold designs shall address freeze protection while
assuring uniform distribution. The manifold shall be designed to minimize drain
down of laterals into other laterals at a lower elevation between dosing
events.
(c)
Lateral pipes shall be three-quarter to two inches in
diameter.
(d)
There shall be no more than a ten per cent difference
in flow rate between the proximal and distal orifices on each distribution
lateral. The system design shall ensure a minimum fluid velocity of two feet
per second is maintained in the main and manifold piping during
dosing.
(e)
There shall be no more than a fifteen per cent
difference in the flow rate between two orifices in different distribution
laterals that are to be dosed simultaneously during a single dosing
event.
(f)
Laterals shall include valves to allow adjustment of
the operating distal pressure at startup to meet design specifications in
compliance with this standard. The distal operating pressure of each lateral
shall be adjusted at startup to ensure compliance with this rule. Baseline
measurements including reconciling the gallons per minute with the design,
distal pressures/heights, and dose rates for future O&M and monitoring must
be measured and recorded before STS approval by the board of
health.
(g)
Low pressure distribution networks shall have an
accessible means of measuring design pressure or operating head for both
initial baseline measurement and future monitoring of orifice clogging and
other network operations and shall include a means of scouring or flushing
distribution laterals.
(2)
Dose frequency
and volume
(a)
Except when the flow restrictive layer is present within
twelve inches of the natural ground surface, each dose shall deliver to the
distribution area no greater than one-fourth of the daily design flow and at
least five times the void volume of the laterals during each twenty-four hour
period. When a flow restrictive layer is present within twelve inches of the
natural ground surface, each dose shall deliver no greater than one-eighth of
the daily design flow and at least three times the void volume of the laterals
during each twenty-four hour period. The board of health may require time
dosing for the design to maximize treatment by control of the instantaneous
loading rate and dose frequency. For split mounds and zoned low pressure
distribution leaching, the dosing frequency shall be equal for each zone within
a twenty-four hour period. The dosing volume shall be based on the soil loading
rate for each mound or zone.
(b)
When time dosing
is used, the selected dose volume and frequency shall ensure that dosing events
are spaced uniformly throughout a twenty-four hour period to maximize resting
between dosing events. Time dosed controls should prevent premature dosing when
less than the daily dose volume is present in the dosing tank.
(3)
Orifices and orifice shielding
(a)
Orifices shall be uniform, clean, and free of all drill
cuttings. Lateral pipes must be stabilized when drilling orifices to prevent
the pipes from moving and to ensure orifices are drilled perpendicular to the
pipe.
(b)
Orifices must be sized no less than one-eighth inch
and spaced a maximum of six feet apart along the lateral.
(c)
The orifice
number and spacing shall provide distribution of no more than six square feet
per orifice with an orifice size of not less than one-eighth inch. Orifices
must be spaced a minimum of six inches from the end of the
lateral.
(d)
The direction of orifices and the method of orifice
shielding shall be specified in the design and shall allow for uniform
pressurization and depressurization of the laterals, and drain-back to prevent
freezing.
(e)
The design must specify how the effluent stream from
the orifices will be dispersed for uniform distribution. When orifices are
positioned up in the twelve o'clock position, the effluent stream must be
sprayed against an orifice shield, gravel-less chambers, or similar device.
When orifices are positioned down in the six o'clock position to facilitate
draining after each dosing cycle, a mechanism to disperse the effluent stream
such as an orifice shield, a pad of gravel, or a splash plate shall be
provided.
(f)
When orifice shields are used, they must be strong
enough to withstand the weight of the backfill and large enough to protect the
orifice from being plugged by gravel.
(g)
If effluent is
to be sprayed upward against the top of gravel-less chambers, the design shall
include and follow manufacturer recommendations.
(4)
The selected
distal pressure to be maintained at the end of each lateral shall be no less
than three feet when using three-sixteenth inch or larger diameter orifices,
and no less than five feet when using orifices smaller than three-sixteenth
inch.
(5)
Pressure dosed STS shall use either elapsed time
meters, event counters, or flow meters capable of measuring total flow to help
determine flow rates and dose volumes. Time dosed STS shall also have control
panels with programmable timers, manual pump operation or hand- off- auto
switches, test features, and as applicable, adjustable override settings.
Adjustable override settings cannot exceed the daily design flow and the
override volume cannot exceed the dosing design of the downstream
component.
(6)
Dosing tanks and pumps and controls must meet the
design and sizing specifications of rule
3701-29-12 of the Administrative
Code. The dosing tank size and the pump, exterior control panel, and alarm
information shall be included with the design. The design shall indicate the
settings or means used to accommodate the dose volume including any drainback
to the dosing tank.
(7)
Testing, setting, adjusting and recording of any low
pressure distribution components and control panel functions shall be conducted
prior to installation approval by the board of health. Flow rate and distal
pressure or operating head shall be consistent with STS design specifications
and a baseline shall be recorded for future performance
monitoring.
(8)
O&M and monitoring devices
(a)
Inspection ports
shall be installed to comply with the following:
(i)
Pressure
distributed leach trenches shall have at least one inspection port placed in
each leaching trench for observation of distribution and any ponding at the
infiltrative surface. The ports shall be anchored and be accessible with at
least a four inch opening and a removable cap; and
(ii)
Mounds shall
have at least three inspection ports spaced at intervals adequate for
observation of distribution and any ponding at the sand fill infiltrative
surface. The ports shall be anchored and be accessible with at least a four
inch opening and a removable cap.
(b)
Accessible
turn-ups shall be provided at the end of each lateral for the purpose of
flushing the laterals and testing distal operating head.
(c)
Shutoff
mechanisms with a durable and stable access port shall be provided to isolate
portions of the distribution network.
(B)
Sewage treatment
systems using low pressure distribution shall be operated, maintained, and
monitored as required by the operation permit issued by the board of health.
The O&M and monitoring of the entire STS shall be conducted at least
annually, or more often as required by a condition of the operation permit. A
service agreement for a STS with a pretreatment component shall also include
the maintenance and monitoring of all system components. In conjunction with
any operation permit conditions or O&M provisions required by the board of
health, the O&M of a sewage treatment system utilizing low pressure
distribution shall include but is not limited to:
(1)
Checking for
ponding in the distribution area;
(2)
Checking for
surface water infiltration or clear water flows from the dwelling or structures
into the system components and around or onto the soil absorption
area;
(3)
Checking the vegetative cover for erosion or settling
and any evidence of settling or seepage in the area of the soil absorption
component;
(4)
Monitoring for proper operation of mechanical
devices;
(5)
Monitoring the dose volume and operating pressure head
of the distribution system and compare to baseline
measurements;
(6)
Flushing of distribution laterals; and
(7)
Review and
document event counters, elapsed time meters, flow meters, and alarm conditions
where present.