Ohio Administrative Code
Title 1501:9 - Division of Mineral Resources Management - Oil and Gas
Chapter 1501:9-10 - Pipelines
Section 1501:9-10-05 - Burial of pipelines
Current through all regulations passed and filed through September 16, 2024
(A) Metallic and nonmetallic pipelines. Excluding all pipelines utilized in the actual drilling or operation of oil and/or natural gas well(s) and pipelines used to transport leasehold gas. No person may lay an oil and/or natural gas pipeline used in the producing of oil and/or natural gas wells that is constructed of metallic or nonmetallic materials unless such pipeline is buried at least twenty-four inches below the ground surface. The owner of such pipeline under this paragraph is exempt from the provisions of this paragraph if the owner finds that:
(B) Whenever a pipeline is laid in accordance with one or more of the above exemptions, the owner of such pipeline will file a statement with the chief of the division of oil and gas resources management identifying: