(A) Upon completion of an installation, the boiler shall be inspected by an inspector . At the time of the inspection, the inspector shall stamp each boiler with a serial number provided to the inspector by the boiler section at the Ohio division of industrial compliance. The stamping shall not be concealed by lagging or paint and shall be exposed at all times. The inspection shall be reported to the superintendent.
(B) A boiler that is subject to inspection shall be prepared for inspection by the owner or user of the boiler when notified by the inspector in accordance with this rule.
(C) The owner or user shall prepare a boiler for internal inspection in the following manner, as applicable:
(D) If a boiler has not been properly prepared for an internal inspection, or the owner or user fails to comply with the requirements for a hydrostatic test as set forth in this chapter, the inspector may decline to make the inspection and no certificate of operation shall be issued or renewed until the boiler has passed an inspection performed by an inspector .
(E) If, in the judgment of the inspector, it is advisable to apply a hydrostatic test to a boiler, the owner or user shall prepare for and apply the test, which shall be witnessed by the inspector.