Section 67-09-01-02 - Construction must be approved by the superintendent of public instruction - Exception

Current through Supplement No. 394, October, 2024

A district may not undertake construction of any school building or facility estimated to cost more than one hundred fifty thousand dollars unless:

1. The construction is approved by the superintendent; or

2. The construction is required as part of a plan to correct deficiencies required under North Dakota Century Code section 15.1-06-09, approved by the state fire marshal, and the estimated cost does not exceed one hundred fifty thousand dollars.

General Authority: NDCC 15.1-36-01

Law Implemented: NDCC 15.1-06-09, 15.1-36-01

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.