All injection wells must be sited in such a fashion that they inject into a formation which has confining zones that are free of known open faults or fractures within the facility area and its delineated area of review.

General Authority: NDCC 38-08-04

Law Implemented: NDCC 38-25

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.