North Dakota Administrative Code
Title 43 - Industrial Commission
Article 43-02 - Mineral Exploration and Development
Chapter 43-02-02 - Subsurface Mineral Exploration and Development
Section 43-02-02-12.4 - Pipeline design and construction requirements

Current through Supplement No. 392, April, 2024

1. Topsoil must be removed before the installation of underground pipelines and replaced after pipelines are installed.

2. Pipeline systems must be constructed with materials that have the strength, thickness, and chemical properties that prevent failure due to pressure gradients, physical contact with the waste or fluids to which the pipes are exposed, climatic conditions, stress of installation, seismic, and stress of daily operation.

3. Design and construction requirements for wellfield pipelines and pipelines between the wellfield and processing and satellite facilities must include an early detection and shutdown capability in the event of pressure drop or loss of flow. This may include automatic motor-operated valves with pressure transmitters and manually operated valves or devices.

General Authority: NDCC 38-12-02

Law Implemented: NDCC 38-12-02

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.