Upon completion of the construction of a surface facility, but before its use, an operator of a well shall certify to the director that the secondary containment area is constructed according to the approved plan. Following advance notice, the director may require an inspection of a surface facility before it is put into service. If an inspection is required it shall be conducted within five business days of the receipt of certification.

General Authority: NDCC 38-12-02

Law Implemented: NDCC 38-12-02

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.