North Dakota Administrative Code
Title 43 - Industrial Commission
Article 43-02 - Mineral Exploration and Development
Chapter 43-02-02.1 - Underground Injection Control Program
Section 43-02-02.1-16 - Schedules of compliance

Current through Supplement No. 392, April, 2024

1. The compliance schedule must require compliance as soon as possible, and not later than three years, after the effective date of the permit.

2. If the compliance schedule is set for a duration of more than one year, interim requirements and completion dates (not to exceed one year) must be incorporated into the compliance schedule and permit.

3. No later than thirty days following each interim and final date, the permittee shall notify the state geologist in writing of compliance/noncompliance.

General Authority: NDCC 38-12-02

Law Implemented: NDCC 38-12-02

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.