STANDARDS FOR FACILITIES OPERATING UNDER A STANDARDIZED PERMIT
Section 33.1-24-05-1062 - Cost estimates for closure
Current through Supplement No. 395, January, 2025
1. The owner or operator must have at the facility a detailed written estimate, in current dollars, of the cost of closing the facility in accordance with the requirements in sections 33.1-24-05-1041 through 33.1-24-05-1045 and applicable closure requirements in sections 33.1-24-05-1086, 33.1-24-05-1111, and 33.1-24-05-1138.
2. During the active life of the facility, the owner or operator must adjust the closure cost estimate for inflation within sixty days prior to the anniversary date of the establishment of the financial instruments used to comply with section 33.1-24-05-1063. For owners and operators using the financial test or corporate guarantee, the closure cost estimate must be updated for inflation within thirty days after the close of the firm's fiscal year and before submission of updated information to the department as specified in paragraph 3 of subdivision b of subsection 6 of section 33.1-24-05-1063. The adjustment may be made by recalculating the maximum costs of closure in current dollars, or by using an inflation factor derived from the most recent implicit price deflator for gross domestic product published by the United States department of commerce in its survey of current business, as specified in subdivisions a and b. The inflation factor is the result of dividing the latest published annual deflator by the deflator for the previous year.
3. During the active life of the facility, the owner or operator must revise the closure cost estimate no later than thirty days after the department has approved the request to modify the closure plan, if the change in the closure plan increases the cost of closure. The revised closure cost estimate must be adjusted for inflation as specified in subsection 2.
4. The owner or operator must keep the following at the facility during the operating life of the facility: The latest closure cost estimate prepared in accordance with subsections 1 and 3 and, when this estimate has been adjusted in accordance with subsection 2, the latest adjusted closure cost estimate.
General Authority: NDCC 23.1-04-03; S.L. 2017, ch. 199, § 1
Law Implemented: NDCC 23.1-04-03, 23.1-04-05, 23.1-04-08; S.L. 2017, ch. 199, § 19