North Dakota Administrative Code
Title 33.1 - Department of Environmental Quality
Article 33.1-20 - Solid Waste Management and Land Protection
Chapter 33.1-20-14 - Financial Assurance Requirements
Section 33.1-20-14-04 - Implementation of financial assurance for closure and postclosure
Universal Citation: ND Admin Code ยง 33.1-20-14-04
Current through Supplement No. 395, January, 2025
1. The closure plan and postclosure plan required by this article must specify the financial assurance mechanisms required by this chapter and, if a trust fund, surety bond, or insurance, the methods and schedules for funding the mechanisms.
2. During the active life of the facility, the owner or operator shall adjust the closure cost estimate and postclosure cost estimate for inflation and shall submit the following information to the department no later than August thirty-first of each year:
a. Updated inflation adjusted closure cost
estimate and postclosure cost estimate;
b. A summary of financial assurance in
place;
c. The submittal date of the
most recent detailed cost estimates for closure and postclosure;
d. The maximum allowed open area and
quantities;
e. Current estimated
open area and quantities; and
f.
The mechanisms in use.
General Authority: NDCC 23.1-08-03; S.L. 2017, ch. 199, § 1
Law Implemented: NDCC 23.1-08-03; S.L. 2017, ch. 199, § 23
Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.