North Dakota Administrative Code
Title 33.1 - Department of Environmental Quality
Article 33.1-20 - Solid Waste Management and Land Protection
Chapter 33.1-20-08 - Disposal of Coal Combustion Residuals in Landfills and Surface Impoundments
Section 33.1-20-08-02 - Applicability

Current through Supplement No. 394, October, 2024

1. The requirements of this chapter apply to owners and operators of new and existing landfills and surface impoundments, including any lateral expansions of such units that dispose or otherwise engage in solid waste management of CCR generated from the combustion of coal at electric utilities and independent power producers. Unless otherwise provided in this chapter, these requirements also apply to disposal units located offsite of the electric utilities and independent power producers. This chapter also applies to any practice that does not meet the definition of a beneficial use of CCR.

2. This chapter does not apply to CCR landfills that have ceased receiving CCR prior to October 19, 2015.

3. This chapter does not apply to electric utilities and independent power producers that have ceased operating prior to October 19, 2015.

4. This chapter does not apply to wastes, including fly ash, bottom ash, boiler slag, and flue gas desulfurization materials generated at facilities that are not part of an electric utility or independent power producer, such as manufacturing facilities, universities, and hospitals. This chapter also does not apply to fly ash, bottom ash, boiler slag, and flue gas desulfurization materials, generated primarily from the combustion of fuels, including other fossil fuels, other than coal, for the purpose of generating electricity unless the fuel burned consists of more than fifty percent coal on a total heat input or mass input basis, whichever results in the greater mass feed rate of coal.

5. This chapter does not apply to practices that meet the definition of a beneficial use of CCR.

6. This chapter does not apply to CCR placement at active or abandoned underground or surface coal mines.

7. This chapter does not apply to municipal solid waste landfills that receive CCR.

8. Owners and operators of CCR units that are subject to this chapter are subject to the solid waste management requirements of this article, unless specifically excluded in other chapters.

9. The owner or operator of an existing CCR unit subject to this chapter, which has a permit that is in effect prior to July 1, 2020, shall apply to the department for a modified permit which meets the requirements of this chapter within twenty-four months of July 1, 2020.

General Authority: NDCC 23.1-08-03

Law Implemented: NDCC 23.1-08-03, 23.1-08-04

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.