North Dakota Administrative Code
Title 33.1 - Department of Environmental Quality
Article 33.1-20 - Solid Waste Management and Land Protection
Chapter 33.1-20-02.1 - Permit Provisions and Procedures
Section 33.1-20-02.1-10 - Solid waste pilot projects

Current through Supplement No. 394, October, 2024

The department may approve applications for solid waste pilot projects that meet the requirements of this section.

1. An applicant shall submit a request for a solid waste pilot project in writing to the department and receive written approval from the department before commencement of any pilot project activities. A pilot project must not exceed two years in length. Persons applying for approval of a pilot project are subject to all local zoning requirements. The department shall maintain a list of all approved solid waste pilot projects and their status on the department's website.

2. Request for pilot project. A pilot project request must include, at a minimum, the following information:

a. General data.
(1) Names, addresses, and telephone numbers of the owner and/or operator;

(2) Legal description, physical address, and mailing address of the proposed site;

(3) Signage to ensure adequate traffic control and a telephone number to contact in case of an emergency;

(4) A provision that the site must be attended or secured during business hours to control public access, prevent unauthorized vehicles, and illegal dumping of wastes; and

(5) A site map drawn to a common, recognized engineering scale illustrating all proposed roads, fencing, existing and proposed structures, adjacent properties, storm water control and containment features, and processing and storage areas.

b. Project overview.
(1) Objectives of the proposed pilot project;

(2) How the pilot project will integrate with an existing or proposed facility;

(3) The methodology and protocol to be used for beneficial use or treatment;

(4) What data will be gathered and what level of results will determine whether the pilot project is successful;

(5) Any analysis to be performed; and

(6) Pilot project time frame. A pilot project may not exceed two years in length from department approval.

c. Operations data.
(1) A description of all feedstock types;

(2) A description of any bulking materials;

(3) A description of any liquid wastes;

(4) A description of proposed use for finished materials and disposition of unfinished materials;

(5) Anticipated volume of all solid and liquid materials to be received and produced during the duration of the pilot project;

(6) A detailed description of the beneficial use or treatment operations;

(7) Access control;

(8) Odor management plan;

(9) Fire protection plan that is in accordance with the local fire codes and requirements;

(10) A description of storm water run-on, runoff, and containment features supported by calculations demonstrating that these features are able to control, at a minimum, a twenty-five-year twenty-four-hour rain event, if precipitation contacts any soluble waste materials;

(11) Recordkeeping for all operational activities;

(12) A description of the work area; and

(13) A contingency plan addressing actions required in the event unacceptable materials are discovered, contamination or discharge of waters from the site occurs, or nuisance conditions occur onsite or offsite.

d. Environmental issues. If the pilot project operations are not conducted indoors or in an area sheltered from the weather, an evaluation of the potential for impacts to ground water and surface water must be provided.

e. Closure plan. A closure plan must be provided describing the actions necessary to adequately close the facility. Closure activities must be completed within thirty days after pilot project completion or termination.

3. Financial assurance. The department may include a requirement for financial assurance to remove materials remaining after closure or for emergency response site cleanup, based on the volume, physical or chemical characteristics, or treatment methods of the materials covered under the pilot project approval.

4. Interim report. For pilot projects that are approved for longer than one year, an interim report must be submitted to the department within thirty days after the first year of the pilot project approval. The interim report must include, at a minimum, the following information:

a. A summary of each objective and whether the objective has been achieved;

b. Identification of anticipated and unanticipated results;

c. Identification of any environmental impacts resulting from the pilot project;

d. Successes and failures; and

e. Data from test results of treated or processed material.

5. Project closeout report. A project closeout report must be submitted to the department within ninety days after pilot project completion or termination. The closeout report must include, at a minimum, the following information:

a. A summary of each objective and whether the objective was achieved;

b. Identification of anticipated and unanticipated results;

c. Identification of any environmental impacts resulting from the pilot project;

d. Successes and failures;

e. Data from test results of treated or processed material; and

f. A description of the closure of pilot project facility.

6. Conversion to permanent facility. To continue operation of a pilot project as a permanent approved solid waste management facility, the owner or operator shall apply for an individual permit or general permit within ninety days of pilot project completion in accordance with chapter 33.1-20-03.1.

General Authority: NDCC 23.1-08-03; S.L. 2023, ch. 254, § 1

Law Implemented: NDCC 23.1-08-03, 23.1-08-09

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.