(a) A petitioner subject to a pre-project vegetation line pursuant to 15A NCAC 07H .0305 may petition the Coastal Resources Commission to approve a Beach Management Plan in accordance with the provisions of this Section. A "petitioner" shall be defined as:
(b) A petitioner shall be eligible to submit a request to approve a Beach Management Plan after the completion of construction of the initial large-scale beach fill project(s) as defined in 15A NCAC 07H .0305 that required the creation of a pre-project vegetation line(s). For a pre-project vegetation line in existence prior to the effective date of this Rule, the award-of-contract date of the initial large-scale beach fill project, or the date of the aerial photography or other survey data used to define the pre-project vegetation line, whichever is most recent, shall be used in lieu of the completion of construction date.
(c) A A Beach Management Plan applies to all pre-project vegetation lines within the Ocean Hazard Area of the petitioner's jurisdiction.
(d) A complete Beach Management Plan shall consist of a comprehensive document with supporting appendices and data that includes the following:
(e) Public Comment Requirements. The local jurisdiction shall provide an opportunity for public comments on the Beach Management Plan prior to submission to the Coastal Resources Commission for approval. Written comments on the Beach Management Plan shall be submitted by the local jurisdiction to the Division along with the request to approve the Beach Management Plan.
(f) A request to approve a Beach Management Plan shall be submitted to the Director of the Division of Coastal Management, 400 Commerce Avenue, Morehead City, NC 28557. Written acknowledgement of the receipt of a completed request, including notification of the date of the meeting at which the request will be considered by the Coastal Resources Commission, shall be provided to the petitioner by the Division of Coastal Management.
(g) The Coastal Resources Commission shall consider a request to approve a Beach Management Plan no later than the second scheduled meeting following the date of receipt of a complete request by the Division of Coastal Management, except when the petitioner and the Division of Coastal Management agree upon a later date.
Authority
G.S.
113A-107;
113A-113(b)(6);
113A-124;
Eff. March
23, 2009;
Amended Eff. April 1, 2016;
Readopted Eff.
September 1, 2021;
Amended Eff. August 1,
2022.