Section 07J .0204 - PROCESSING THE APPLICATION
Current through Register Vol. 39, No. 6, September 16, 2024
(a) On receipt of a CAMA major development and/or dredge and fill permit application by the Department, a letter shall be sent to the applicant acknowledging receipt.
(b) Application processing shall begin when an application is accepted as complete. Before an application will be accepted as complete, the following requirements must be met;
(c) Upon acceptance of a major development and/or dredge and fill permit as complete, the Department shall send a letter to the applicant setting forth the data on which acceptance was made.
(d) If the application is found to be incomplete or inaccurate after processing has begun or if additional information from the applicant is necessary to adequately assess the project, the processing shall be terminated pending receipt of the necessary changes or necessary information from the applicant. During the pendency of any termination of processing, the permit processing period shall not run. If the changes or additional information significantly alters the project proposal, the application shall be considered new and the permit processing period will begin to run from that date.
(e) Any violation occurring at a proposed project site for which an application is being reviewed shall be processed according to the procedures in 15A NCAC 07J .0408 - 0410. If the violation substantially altered the proposed project site, and restoration is deemed necessary, the applicant shall be notified that processing of the application will be suspended pending compliance with the notice of required restoration. Satisfactory restoration of any unauthorized development that has substantially altered a project site is deemed necessary to allow a complete review of the application and an accurate assessment of the project's potential impacts. The applicant shall be notified that permit processing has resumed, and that a new processing deadline has been established once the required restoration has been deemed satisfactory by the Division of Coastal Management or Local Permit Officer.
(f) If during the public comment period a question is raised as to public rights of access across the subject property, the Division of Coastal Management shall examine the access issue prior to making a permit decision. Any individual or governmental entity initiating action to judicially recognize a public right of access must obtain a court order to suspend processing of the permit application. Should the parties to legal action resolve the issue, permit processing shall continue.
Authority
G.S.
113-229;
113A-119;
113A-119.1;
113A-122(c);
113A-124;
Eff. March
15, 1978;
Amended Eff. November 1, 1991; March 1, 1991; July 1,
1990; July 1, 1989;
Temporary Amendment Eff. September 2,
1998;
Temporary Amendment Expired June 28, 1999;
Amended Eff. August 1, 2000.