(a) Conductor casing design and setting depth shall be based on the geological conditions at the wellbore location, including the presence or absence of hydrocarbons and potential drilling hazards.
(b) Conductor casing shall be cemented from bottom to top, with return to the surface. If cement does not return to the surface, the permittee shall consult with and obtain approval from the Department to determine the appropriate method to emplace cement.
(c) Conductor casing shall:
(d) A mechanical or cement seal shall be installed at the surface to block downward migration of surface pollutants.
Authority
G.S.
113-391(a)(5)c;
Eff. March 17, 2015.