Section 02Q .0501 - PURPOSE OF SECTION AND REQUIREMENT FOR A PERMIT
Current through Register Vol. 39, No. 6, September 16, 2024
(a) The purpose of this Section is to establish an air quality permitting program as required pursuant to Title V of the Clean Air Act and 40 CFR Part 70.
(b) With the exception in Paragraph (c) of this Rule, the owner or operator of an existing facility, new facility, or modification of an existing facility (except for minor modifications pursuant to 15A NCAC 02Q .0515), including significant modifications that would not contravene or conflict with a condition in the existing permit, shall not begin construction without first obtaining:
(c) If the owner or operator proposes to make a significant modification pursuant to 15A NCAC 02Q .0516 that would contravene or conflict with a condition in the existing permit, the owner or operator shall not begin construction or make the modification until the owner or operator has obtained:
(d) All facilities subject to this Section shall have a permit to operate that assures compliance with 40 CFR Part 70 and all applicable federal and State requirements.
(e) Except as allowed pursuant to 15A NCAC 02Q .0515(f) (minor modifications), no facility subject to the requirements of this Section may operate after the time that it is required to submit a timely and complete application pursuant to this Section except in compliance with a permit issued pursuant to this Section. This Paragraph does not apply to to permit renewals pursuant to 15A NCAC 02Q .0513.
(f) If the conditions of 15A NCAC 02Q .0512(b) (application shield) are met, the facility's failure to have a permit pursuant to this Section shall not be a violation of operating without a permit.
(g) If the owner or operator of a facility subject to the requirements of this Section submits an application for a revision to his permit before receiving the initial permit pursuant to this Section, the application for the revision shall be processed pursuant to 15A NCAC 02Q .0300.
(h) The owner or operator of a facility or source subject to the requirements of this Section may also be subject to the toxic air pollutant procedures set forth in 15A NCAC 02Q .0700.
(i) The owner or operator of an affected unit subject to the acid rain program requirements of Title IV is also subject to the procedures pursuant to 15A NCAC 02Q .0400.
(j) The owner or operator of a facility subject to the requirements of this Section shall pay permit fees in accordance with the requirements of 15A NCAC 02Q .0200.
Authority
G.S.
143-215.3(a)(1);
143-215.107(a)(10);
143-215.108;
Temporary Adoption Eff. March 8, 1994 for a period of 180 days or until the
permanent rule becomes effective, whichever is sooner;
Eff. July 1,
1994;
Amended Eff. July 1, 1998; July 1, 1996;
Readopted Eff. April 1, 2018.