North Carolina Administrative Code
Title 15A - Environmental Quality
Chapter 02 - ENVIRONMENTAL MANAGEMENT
Subchapter N - CRITERIA AND STANDARDS APPLICABLE TO UNDERGROUND STORAGE TANKS
Section .0400 - GENERAL OPERATING REQUIREMENTS
Section 02N .0406 - PERIODIC TESTING OF SPILL PREVENTION EQUIPMENT AND CONTAINMENT SUMPS USED FOR INTERSTITIAL MONITORING OF PIPING AND PERIODIC INSPECTION OF OVERFILL PREVENTION EQUIPMENT

Universal Citation: 15A NC Admin Code 02N .0406

Current through Register Vol. 39, No. 6, September 16, 2024

The regulations governing "Periodic testing of spill prevention equipment and containment sumps used for interstitial monitoring of piping and periodic inspection of overfill prevention equipment" set forth in 40 CFR 280.35 are hereby incorporated by reference, excluding any subsequent amendments and editions, except that:

(1) UST system or UST system component installations or replacements completed on or after November 1, 2007, shall meet the requirements of Section .0900 of this Subchapter.

(2) Tank owners and operators may use test methods and testing equipment approved by the US Environmental Protection Agency pursuant to 40 CFR 280.35(a)(1)(ii)(C) to meet the requirements of 40 CFR 280.35(a)(1)(ii).

Authority G.S. 143-215.3(a)(15); 143B-282(a)(2)(h);
Eff. June 1, 2017;
Amended Eff. August 23, 2022; January 1, 2021.

Disclaimer: These regulations may not be the most recent version. North Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.