The applicant shall submit a construction schedule that includes:
(1) Techniques and work force to be used to insure that the dam is constructed according to the plans and specifications;
(2) A construction schedule that includes the estimated time to complete the construction activities;
(3) Techniques to be used to divert the stream flow to prevent interference with construction and hazard to life, health, or property;
(4) The extent and method of quality control shall be subject to approval of the Director.