Section .0700 - NUCLEAR POWER SYSTEMS
Section 13 .0703 - INSERVICE INSPECTION

Universal Citation: 13 NC Admin Code 13 .0703
Current through Register Vol. 39, No. 6, September 16, 2024

The owner/operator of an operating nuclear power plant shall have a contract with an Authorized Inspection Agency who will be responsible for ASME Code, Section III and Section XI third party code inspections. It is the duty of the ANI and Authorized Nuclear In-service Inspector (ANII), as applicable, to make all of the inspections specified by the rules of the ASME Code, Section III, Section XI and ASME QAI-1, and any other inspections and tests necessary to verify that the equipment is inspected, examined, repaired or replaced in accordance with requirements of the ASME Code.

Authority G.S. 95-69.11; 95-69.14;
Eff. May 29, 1981;
Amended Eff. July 1, 2006;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.

Disclaimer: These regulations may not be the most recent version. North Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.