Section .0700 - NUCLEAR POWER SYSTEMS
Section 13 .0702 - INSPECTION DURING CONSTRUCTION

Universal Citation: 13 NC Admin Code 13 .0702
Current through Register Vol. 39, No. 6, September 16, 2024

The constructor of a nuclear power plant shall have a contract with an Authorized Inspection Agency who will be responsible for ASME Code, Section III third party code inspections. It is the duty of the Authorized Nuclear Inspector (ANI) to conduct all of the inspections specified by the rules of the ASME Code, Section III and ASME QAI-1,in addition to such other inspections and tests as in his judgment are necessary to verify that the equipment is fabricated and installed in accordance with requirements of the ASME Code and these Rules.

Authority G.S. 95-69.11; 95-69.14;
Eff. May 29, 1981;
Amended Eff. July 1, 2006;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.

Disclaimer: These regulations may not be the most recent version. North Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.