North Carolina Administrative Code
Title 04 - COMMERCE
Chapter 11 - UTILITIES COMMISSION
Chapter 8
Article 7 - POWER RELIABILITY
Section 11 R08-40A - SERVICE RELIABILITY INDEX REPORTING

Universal Citation: 7 NC Admin Code 11 R 08-40A

Current through Register Vol. 39, No. 6, September 16, 2024

(a) Purpose. The purpose of this Rule is to establish standards for measuring and reporting distribution service reliability by electric public utilities that own and operate electric power distribution systems in North Carolina.

(b) Applicability. This Rule applies to Duke Energy Carolinas, LLC; Duke Energy Progress, Inc.; and Dominion North Carolina Power.

(c) Definitions. Unless otherwise provided for in this Rule, all terms used are as defined by the Institute of Electrical and Electronics Engineers (IEEE) in the most current IEEE Guide for Electric Power Distribution Reliability Indices 1366 (IEEE Standard 1366).

(d) Quarterly Reports.

(1) Each electric public utility shall report service reliability data to the Commission on a quarterly basis. The data reported shall be submitted within 30 days of the end of each quarter and shall reflect SAIDI and SAIFI results for the preceding 12 months.

(2) SAIDI and SAIFI shall be calculated in accordance with IEEE Standard 1366.

(3) The reports shall include: SAIDI, with and without Major Event Days, and SAIFI, with and without Major Event Days.

(4) Interruptions reported shall include all sustained interruptions, except those for Major Event Days.

NCUC Docket No. E-100, Sub 138, 11/25/13

Disclaimer: These regulations may not be the most recent version. North Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.