Current through Register Vol. 39, No. 6, September 16, 2024
(a) Purpose. -
The purpose of this rule is to implement the provisions of
G.S.
62-110.8, and to provide for Commission
oversight of the CPRE Program(s) designed by the electric public utilities
subject to
G.S.
62-110.8 for the competitive procurement and
development of renewable energy facilities in a manner that ensures continued
reliable and cost-effective electric service to customers in North
Carolina.
(b) Definitions.
(1) "Affiliate" is defined as provided in
G.S.
62-126.3(1).
(2) "Avoided cost rates" - means an electric
public utility's calculation of its long-term, levelized avoided energy and
capacity costs utilizing the methodology most recently approved or established
by the Commission as of 30 days prior to the date of the electric public
utility's upcoming CPRE RFP Solicitation for purchases of electricity from
qualifying facilities pursuant to Section 210 of the Public Utility Regulatory
Policies Act of 1978, as amended. The electric public utility's avoided cost
rates shall be used for purposes of determining the cost effectiveness of
renewable energy resources procured through a CPRE RFP Solicitation. With
respect to each CPRE RFP Solicitation, the electric public utility's avoided
costs shall be calculated over the time period of the utility's pro forma
contract(s) approved by the Commission.
(3) "Competitive Procurement of Renewable
Energy (CPRE) Program" means the program(s) established by
G.S.
62-110.8 requiring Duke Energy Carolinas,
LLC, and Duke Energy Progress, LLC, to jointly or individually procure an
aggregate 2,660 megawatts (MW) of renewable energy resource nameplate capacity
subject to the requirements and limitations established therein.
(4) "CPRE Program Methodology" means the
methodology used to evaluate all proposals received in a given CPRE RFP
Solicitation.
(5) "CPRE Program
Procurement Period" means the initial 45-month period in which the aggregate
2,660 MW of renewable energy resource nameplate capacity is required to be
procured under the CPRE Program(s) approved by the Commission.
(6) "CPRE RFP Solicitation" means a request
for proposal solicitation process to be followed by the electric public utility
under this Rule for the competitive procurement of renewable energy resource
capacity pursuant to the utility's CPRE Program.
(7) "Evaluation Team" means employees and
agents of an electric public utility that will be evaluating proposals
submitted in response to the CPRE RFP Solicitation, including those acting for
or on behalf of the electric public utility regarding any aspect of the CPRE
RFP Solicitation evaluation or selection process.
(8) "IA Website" means the website
established and maintained by the Independent Administrator as required by
subsection (d)(7) of this Rule.
(9)
"Independent Administrator" means the third-party entity to be approved by the
Commission that is responsible for independently administering the CPRE Program
in accordance with
G.S.
62-110.8 and this rule, developing and
publishing the CPRE Program Methodology, and for ensuring that all responses to
a CPRE RFP Solicitation are treated equitably.
(10) "Electric public utility" means an
electric public utility that is required to comply with the requirements of
G.S.
62-110.8.
(11) "Market participant" means a person who
has expressed interest in submitting a proposal in response to a CPRE RFP
Solicitation or has submitted such a proposal, including, unless the context
requires otherwise, an Affiliate or an electric public utility, through its
Proposal Team.
(12) "Proposal Team"
means employees and agents of an electric public utility or an Affiliate that
proposes to meet a portion of its CPRE Program requirements as provided in
G.S.
62-110.8(b)(i) or (ii),
which is more particularly described as a "Self-developed Proposal" in
subsection (f)(2)(iv) of this rule, who directly support the Self-developed
Proposal.
(13) "Renewable energy
certificate" is defined as provided in
G.S.
62-133.8(a)(6).
(14) "Renewable energy facility" means an
electric generating facility that uses renewable energy resource(s) as its
primary source of fuel, has a nameplate capacity rating of 80 MW or less, and
is placed into service after the beginning of the CPRE Program Procurement
Period.
(15) "Renewable energy
resource" is as defined as provided in
G.S.
62-133.8(a)(8).
(16) "T&D Sub-Team" means those members
of the Evaluation Team responsible for assessing the impacts of proposals on
the electric public utility's transmission and distribution systems and
assigning any system upgrade costs attributable to each proposal pursuant to
R8-71(f)(3)(iii). The T&D Sub-Team shall be designated in writing to the
Independent Administrator and shall have no communication, either directly or
indirectly, with the other members of the Evaluation Team or a market
participant concerning any proposal, except through the Independent
Administrator, from the date on which the draft CPRE RFP Solicitation documents
are issued by the Independent Administrator until the CPRE RFP Solicitation is
deemed closed.
(c)
Initial CPRE Program Filings and Program Guidelines
(1) Each electric public utility shall
develop and seek Commission approval of guidelines for the implementation of
its CPRE Program and to inform market participants regarding the terms and
conditions of, and process for participating in, the CPRE Program. The electric
public utility shall file its initial CPRE Program guidelines at the time it
initially proposes a CPRE Program for Commission approval. The CPRE Program
guidelines should, at minimum, include the following:
(i) Planned allocation between the electric
public utilities of the 2,660 MW required to be procured during the CPRE
Program Procurement Period;
(ii)
Proposed timeframe for each electric public utility's initial CPRE RFP
Solicitation(s) and planned initial procurement amount, as well as plans for
additional CPRE RFP Solicitation(s) during the CPRE Program Procurement
Period;
(iii) Minimum requirements
for participation in the electric public utility's initial CPRE RFP
Solicitation(s);
(iv) Proposed
evaluation factors, including economic and noneconomic factors, for the
evaluation of proposals submitted in response to CPRE RFP Solicitation(s);
and
(v) Pro forma contract(s) to be
utilized in the CPRE Program.
(2) At the time an electric public utility
files its proposed CPRE Program guidelines with the Commission, it shall also
identify any regulatory conditions and/or provisions of the electric public
utility's code of conduct that the electric public utility seeks to waive for
the duration of the CPRE Program Procurement Period pursuant to
G.S.
62-110.8(h)(2).
(d) Selection and Role of
Independent Administrator.
(1) In advance of
the filing the initial CPRE Program required by subsection (c) of this Rule,
the Commission shall invite and consider comments and recommendations from the
electric public utilities, the Public Staff, and other interested persons,
including market participants, regarding the selection of the Independent
Administrator. In addition to the requirements in this Rule, the Commission may
establish additional minimum qualifications and requirements for the
Independent Administrator.
(2) Any
person requesting to be considered for approval as the Independent
Administrator shall be required to disclose any financial interest involving
the electric public utilities implementing CPRE Programs or any market
participant, including, but not limited to, all substantive assignments for
electric public utilities, Affiliate(s), or market participant during the
preceding three (3) years.
(3) In
advance of the initial CPRE RFP Solicitation(s), the Commission shall select
and approve the Independent Administrator. From the date the Independent
Administrator is selected, no market participant shall have any communication
with the Independent Administrator or the electric public utility pertaining to
the CPRE RFP Solicitation, the RFP documents and process, or the evaluation
process or any related subjects, except as those communications are
specifically allowed by this rule.
(4) The Independent Administrator will be
retained by the electric public utility or jointly by the electric public
utilities for the duration of the CPRE Program Procurement Period under a
contract to be filed with the Commission at least sixty (60) days prior to the
public utilities' initial CPRE RFP Solicitation(s). The Independent
Administrator shall remain subject to ongoing Commission oversight as part of
the Commission's review of the electric public utilities' annual CPRE Program
Compliance Reports.
(5) The
Independent Administrator's duties shall include:
(i) Monitor compliance with CPRE Program
requirements.
(ii) Review and
comment on draft CPRE Program filings, plans, and other documents.
(iii) Facilitate and monitor permissible
communications between the electric public utilities' Evaluation Team and other
participants in the CPRE RFP solicitations.
(iv) Develop and publish the CPRE Program
Methodology that shall ensure equitable review between an electric public
utility's Self-developed Proposal(s) as addressed in subsection (f)(2)(iv) and
proposals offered by third-party market participants.
(v) Receive and transmit proposals.
(vi) Independently evaluate the
proposals.
(vii) Monitor
post-proposal negotiations between the electric public utilities' Evaluation
Team(s) and participants who submitted winning proposals.
(viii) Evaluate the electric public utility's
Self-developed Proposals.
(ix)
Provide an independent certification to the Commission in the CPRE Compliance
Report that all electric public utility and third party proposals were
evaluated under the published CPRE Program methodology and that all proposals
were treated equitably through the CPRE RFP Solicitation(s).
(6) Prior to the initial CPRE RFP
Solicitation, but on or before the date determined by Commission order,
Independent Administrator shall develop and publish the CPRE Program
Methodology. Prior to developing and publishing the CPRE Program Methodology,
the Independent Administrator shall meet with the Evaluation Team(s) to share
evaluation techniques and practices. The Independent Administrator shall also
meet with the Evaluation Team(s) at least 60 days prior to each subsequent CPRE
RFP Solicitation to discuss the efficacy of the CPRE Program Methodology and
whether changes to the CPRE Program Methodology may be appropriate based upon
the anticipated contents of the next CPRE RFP Solicitation. If the CRPE RFP
Solicitation allows for electric public utility self-build options or Affiliate
proposals, the Independent Administrator shall ensure that if any non-publicly
available transmission or distribution system information is used in preparing
proposals by the electric public utility or Affiliate(s), such information is
made available to third parties that notified the Independent Administrator or
their intent to submit a proposal in response to the that CPRE RFP
Solicitation.
(7) The Independent
Administrator shall maintain the IA Website to support administration and
implementation of the CPRE Program and shall post the CPRE RFP Solicitation
documents, the CPRE Program Methodology, participant FAQs, and any other
pertinent documents on the IA Website.
(8) In carrying out its duties, the
Independent Administrator shall work in coordination with the Evaluation
Team(s) with respect to CPRE Program implementation and the CPRE RFP
Solicitation proposal evaluation process in the manner and to the extent as
more specifically provided in subsection (f) of this rule.
(9) If the Independent Administrator becomes
aware of a violation of any CPRE Program requirements, the Independent
Administrator shall immediately report that violation, together with any
recommended remedy, to the Commission.
(10) The Independent Administrator's fees
shall be funded through reasonable proposal fees collected by the electric
public utility. The electric public utility shall be authorized to collect
proposal fees up to $10,000 per proposal to defray its costs of evaluating the
proposals. In addition, the electric public utility may charge each participant
an amount equal to the estimated total cost of retaining the Independent
Administrator divided by the reasonably anticipated number of proposals. To the
extent that insufficient funds are collected through these methods to pay of
the total cost of retaining the Independent Administrator, the electric public
utility shall pay the balance and subsequently charge the winning participants
in the CPRE RFP Solicitation.
(e) Communications Between CPRE Market
Participants.
(1) From the date an electric
public utility announces a CPRE RFP Solicitation, until the Independent
Administrator declares the CPRE RFP Solicitation closed, there shall be no
communications between market participants regarding the substantive aspects of
their proposals or between the electric public utility and market participants.
Such communications shall be conducted through the Independent Administrator as
permitted by this subsection.
(2)
The Evaluation Team or the Independent Administrator may request further
information from any market participant regarding its proposal during the
process of evaluating and selecting proposals. These communications shall be
conducted through the Independent Administrator and shall be conducted in a
manner that keeps confidential the identity of the market
participant.
(3) On or before the
date an electric public utility announces a CPRE RFP Solicitation, the Proposal
Team shall be separately identified and physically segregated from the
Evaluation Team for purposes of all activities that are part of the CPRE RFP
Solicitation process. The names and job titles of each member of the Proposal
Team and the Evaluation Team shall be reduced to writing and submitted to the
Independent Administrator.
(4)
There shall be no communications, either directly or indirectly, between the
Proposal Team and Evaluation Team during the CPRE RFP Solicitation regarding
any aspect of the CPRE RFP Solicitation process, except (i) necessary
communications as may be made through the Independent Administrator and (ii)
negotiations between the Proposal Team and the Evaluation Team for a final
power purchase agreement after the Proposal Team has been selected by the
electric public utility as a winning proposal. The Evaluation Team will have no
direct or indirect contact or communications with the Proposal Team or any
other participant, except through the Independent Administrator as described
further herein, until such time as a winning proposal or proposals are selected
by the electric public utility and negotiations for a final power purchase
agreement(s) have begun.
(5) At no
time shall any information regarding the CPRE RFP Solicitation process be
shared with any market participant, including the Proposal Team, unless the
information is shared with all competing participants contemporaneously and in
the same manner.
(6) Within fifteen
(15) days of the date an electric public utility announces a planned CPRE RFP
Solicitation, each member of the Proposal Team shall execute an acknowledgement
that he or she agrees to abide by the restrictions and conditions contained in
subsection (e) of this rule for the duration of the CPRE RFP Solicitation. If
the Proposal Team's proposal is selected by the electric public utility after
completion of the CPRE RFP Solicitation, each member of the Proposal Team shall
then also execute an acknowledgement that he or she has met the restrictions
and conditions contained in subsection (e) of this rule. The electric public
utility shall provide these acknowledgements to the Independent Administrator
and shall file the acknowledgements with the Commission in support of its
annual CPRE Compliance Report.
(7)
Should any participant, including an Affiliate or electric public utility's
Proposal Team, attempt to contact a member of the Evaluation Team directly,
such participant shall be directed to the Independent Administrator for all
information and such communication shall be reported to the Independent
Administrator by the Evaluation Team member. Within ten (10) days of the date
that the Independent Administrator issues the CPRE RFP Solicitation, each
Evaluation Team member shall execute an acknowledgement that he or she agrees
to abide by the conditions contained in subsection (e) of this rule for the
duration of the CPRE RFP Solicitation. If the Proposal Team's proposal is
selected by the electric public utility after completion of the CPRE RFP
Solicitation, the Evaluation Team shall also execute an acknowledgement that he
or she has met the restrictions and conditions contained in subsection
(e)(3)-(5) above. The electric public utility shall provide these
acknowledgements to the Independent Administrator and shall file the
acknowledgements with the Commission in support of its annual CPRE Compliance
Report.
(f) CPRE RFP
Solicitation Structure and Process.
(1)
Identification of Market Participants; Design of CPRE RFP Solicitation.
(i) Prior to the initial CPRE RFP
Solicitation, the electric public utility shall provide the Independent
Administrator with a list of potential market participants that have expressed
interest, in writing, in participating in the CPRE RFP Solicitation or have
participated in recent renewable energy resource solicitations issued by the
electric public utilities. The Independent Administrator shall publish notice
of the draft CPRE RFP Solicitation on the IA Website, and prepare the list of
potential participants to whom notice of the upcoming CPRE RFP Solicitation
will be sent.
(ii) The electric
public utility shall prepare an initial draft of the CPRE RFP Solicitation
guidelines and documents, including RFP procedures, evaluation factors, credit
and security obligations, a pro forma power purchase agreement, the Avoided
Cost Rate against which proposals will be evaluated, and a planned schedule for
completing the CPRE RFP Solicitation and selecting winning proposals. No later
than sixty (60) days prior to the planned issue date of the CPRE RFP
Solicitation, the electric public utility shall provide the initial draft of
the CPRE RFP Solicitation guidelines and documents to the Independent
Administrator for posting on the IA Website.
(iii) The evaluation factors included in the
CPRE RFP Solicitation guidelines shall identify all economic and noneconomic
factors to be considered by the Independent Administrator in its evaluation of
proposals. In addition to the guidelines, a pro forma power purchase agreement
containing all expected material terms and conditions shall be included in the
CPRE RFP Solicitation documents provided to the Independent Administrator and
shall be filed with the Commission at least thirty (30) days prior to the
planned CPRE RFP solicitation issuance date.
(iv) The Independent Administrator, in
coordination with the electric public utility, may conduct a pre-issuance
market participants' conference to publicly discuss the draft CPRE RFP
Solicitation guidelines and documents with market participants. Market
participants may submit written questions or recommendations to the Independent
Administrator regarding the draft CPRE RFP Solicitation guidelines and
documents in advance of the market participants' conference. All such questions
and recommendations shall be posted on the IA Website. The Independent
Administrator shall have no private communication with any potential
participants regarding any aspect of the draft CPRE RFP Solicitation
documents.
(v) Based on the input
received from potential participants, and on its own review of the draft CPRE
RFP Solicitation documents, the Independent Administrator shall submit a report
to the electric public utility, at least twenty (20) days prior to the planned
CPRE RFP Solicitation issuance date, detailing market participants' comments
and the Independent Administrator's recommendations for changes to the CPRE RFP
Solicitation documents, if any. This report shall also be posted on the IA
Website for review by potential participants.
(vi) At least five (5) days prior to the
planned CPRE RFP Solicitation issuance date, the electric public utility shall
submit its final version of the CPRE RFP Solicitation documents to the
Independent Administrator to be posted on the IA Website.
(vii) At any time after the CPRE RFP
Solicitation is issued, through the time winning proposals are selected by the
electric public utility, the schedule for the solicitation may be modified upon
mutual agreement of the electric public utility and the Independent
Administrator, with equal notice provided to all market participants, or upon
approval by the Commission. Any modification to the CPRE RFP Solicitation
schedule will be posted to the IA Website.
(2) Issuance of CPRE RFP Solicitation.
(i) The Independent Administrator shall
transmit the final CPRE RFP Solicitation to the market participants via the IA
Website. Upon issuance of the final CPRE RFP Solicitation, the only
communications permitted prior to submission of proposals shall be conducted
through the Independent Administrator. Participants' questions and the
Independent Administrator's responses shall be posted on the IA Website, but,
to the extent possible, shall be posted in a manner that the identity of the
participant remains confidential. To the extent such questions and responses
contain competitively sensitive information that a particular participant deems
to be a trade secret, this information may be redacted by the
participant.
(ii) The electric
public utility shall not communicate with any market participant regarding the
RFP Process, the content of the CPRE RFP Solicitation documents, or the
substance of any potential response by a participant to the RFP; provided,
however, the electric public utility shall provide timely, accurate responses
to the Independent Administrator's request for information regarding any aspect
of the CPRE RFP Solicitation documents or the CPRE RFP Solicitation
process.
(iii) Participants shall
submit proposals pursuant to the solicitation schedule contained in the CPRE
RFP Solicitation, and in the format required by the Independent Administrator
to facilitate the evaluation and selection of proposals. The Independent
Administrator shall have access to all proposals and all supporting
documentation submitted by market participants in the course of the CPRE RFP
Solicitation process.
(iv) If the
electric public utility wishes to consider an option for full or partial
ownership of a renewable energy facility as part of the CPRE RFP solicitation,
the utility must submit its construction proposal (Self-developed Proposal) to
provide all or part of the capacity requested in the CPRE RFP solicitation to
the Independent Administrator at the time all other proposals are due. Once
submitted, the Self-developed Proposal may not be modified, except in the event
that the electric public utility demonstrates to the satisfaction of the
Independent Administrator that the Self-developed Proposal contains an error
and that correction of the error will not be unduly harmful to the other market
participants, the electric public utility may correct the error. Persons who
have participated or assisted in the preparation of the Self-developed Proposal
on behalf of the electric public utility's Proposal Team in any way may not be
a member of the Affiliate's Proposal Team, nor communicate with the Affiliate's
Proposal Team during the RFP Process about any aspect of the RFP
Process.
(3) Evaluation
and Selection of Proposals. The evaluation and selection of proposals received
in response to a CPRE RFP Solicitation shall proceed in two steps as set forth
in this subdivision, and shall be subject to the Commission's oversight as
provided in
G.S.
62-110.8 and this rule.
(i) In step one, the Independent
Administrator shall evaluate all proposals based upon the CPRE RFP Solicitation
evaluation factors using the CPRE Program Methodology. The Independent
Administrator shall conduct this evaluation in an appropriate manner designed
to ensure equitable review of all proposals based on the economic and
noneconomic factors contained in the CPRE RFP Solicitation evaluation factors.
As a result of the Independent Administrator's evaluation, the Independent
Administrator shall, subject to the provisions of subsection (f)(3)(ii) of this
Rule, eliminate proposals that fail to meet the CPRE RFP Solicitation
evaluation factors and then develop and deliver to the electric public
utility's T&D Sub-Team a list of proposals ranked in order from most
competitive to least competitive. The Independent Administrator shall redact
from the proposals included in the list delivered to the electric public
utility any information that identifies the market participant that submitted
the proposal and any information in the proposal that is not reasonably
necessary for the utility to complete step two of the evaluation process,
including economic factors such as cost and pricing information.
(ii) As a part of the step one evaluation,
the Independent Administrator may, in its discretion, allow a market
participant to modify or clarify its proposal to cure a non-conformance that
would otherwise require elimination of the proposal, and may consult with the
electric public utility's Evaluation Team to determine whether a proposal meets
the CPRE RFP Solicitation Evaluation factors. In consulting with the Evaluation
Team, the Independent Administrator shall maintain the anonymity of the market
participant that submitted the proposal. The Independent Administrator shall
document the reasons for the elimination of a proposal.
(iii) In step two, the electric public
utility's T&D Sub-Team shall assess the system impact of the proposals in
the order ranked by the Independent Administrator and assign any system upgrade
costs attributable to each proposal included in the list provided by the
Independent Administrator. The T&D Sub-Team shall conduct this assessment
in a reasonable manner, with oversight by the Independent Administrator, and in
parallel with the Independent Administrator's allowing modification or
clarification of proposals and consultation with the Evaluation Team, as
provided in (f)(3)(ii), if applicable. The electric public utility's T&D
Sub-Team shall provide its assessment of system upgrade costs to the
Independent Administrator, who shall first determine whether such system
upgrade costs have been appropriately assigned and then determine whether the
original ranking of proposals needs to be modified to recognize the system
upgrade costs assigned to each proposal. The Independent Administrator shall
also eliminate any proposal where necessary in order to comply with
G.S.
62-110.8(b)(4). If no
re-ranking is needed and the Independent Administrator has concluded its
evaluation pursuant to (f)(3)(ii) of this Rule, if applicable, then the
electric public utility shall select the winning proposals in accordance with
subsection (iv) below. If the Independent Administrator modifies the original
ranking as result of the assignment of system upgrade costs or the elimination
of a proposal, it shall deliver to the T&D Sub-Team of the electric public
utility such revised list of proposals ranked in order from most competitive to
least competitive (with market participant information redacted as described in
step one) and the assignment of system upgrade costs described in this
subsection shall be performed again by the T&D Sub-Team and provided to the
Independent Administrator, who will re-rank the proposals. This process shall
continue on an iterative basis, as directed by the Independent Administrator,
until the Independent Administrator determines that the total generating
capacity sought in the CPRE RFP Solicitation is satisfied in the most
cost-effective manner after taking into account the assignment of system
upgrade costs through this step two.
(iv) Upon completion of step two and
determination by the Independent Administer of the final ranking of the
proposals, the Independent Administrator shall deliver to the Evaluation Team
of the electric public utility the final ranked list of proposals. The electric
public utility shall select proposals in the order ranked by the Independent
Administrator until the total generating capacity sought in the CPRE RFP
Solicitation is satisfied, and the Independent Administrator shall provide the
electric public utility with the identity of the market participants that were
so selected. Upon publication of the list of proposals selected, the
Independent Administrator shall declare the CPRE RFP Solicitation
closed.
(v) The electric public
utility shall proceed to execute contracts (where applicable) with each of the
market participants who submitted a proposal that was selected. If a market
participant selected pursuant to subsection (iv) fails to execute a contract
during the contracting period identified in the CPRE RFP Solicitation, the
electric public utility shall provide to the Independent Administrator a short
and plain explanation regarding such failure and the Independent Administrator,
after consultation with the Evaluation Team, shall determine whether the
next-ranked proposal or proposals should be selected in order to procure the
total generating capacity sought in the CPRE RFP Solicitation. For the
avoidance of doubt, the Evaluation Team shall not have access to the
identifying information of any such proposals prior to the Independent
Administrator's determination. If no additional proposals are selected, the
capacity amount associated with the proposal of the market participant that
failed to execute a contract shall be included in a subsequent CPRE RFP
Solicitation; provided that if, no further CPRE RFP Solicitations are
scheduled, the electric public utility shall take such action as is directed by
the Commission.
(g) CPRE Program Plan.
(1) Each electric public utility shall file
its initial CPRE Program plan with the Commission at the time initial CPRE
Program Guidelines are filed under subsection (c) and thereafter shall be filed
on or before September 1 of each year. The electric public utility may file its
CPRE Program plan as part of its future biennial integrated resource plan
filings, or update thereto, and the CPRE Program plan filed pursuant to this
rule will be reviewed in the same docket as the electric public utility's
biennial integrated resource plan or update filing.
(2) Each year, beginning in 2018, each
electric public utility shall file with the Commission an updated CPRE Program
plan covering the remainder of the CPRE Program Procurement Period. At a
minimum, the plan shall include the following information:
(i) an explanation of whether the electric
public utility is jointly or individually implementing the aggregate CPRE
Program requirements mandated by
G.S.
62-110.8(a);
(ii) a description of the electric public
utility's planned CPRE RFP Solicitations and specific actions planned to
procure renewable energy resources during the CPRE Program planning
period;
(iii) an explanation of how
the electric public utility has allocated the amount of CPRE Program resources
projected to be procured during the CPRE Program Procurement Period relative to
the aggregate CPRE Program requirements;
(iv) if designated by location, an
explanation of how the electric public utility has determined the locational
allocation within its balancing authority area;
(v) an estimate of renewable energy
generating capacity that is not subject to economic dispatch or economic
curtailment that is under development and projected to have executed power
purchase agreements and interconnection agreements with the electric public
utility or that is otherwise projected to be installed in the electric public
utility's balancing authority area within the CPRE Program planning period;
and
(vi) a copy of the electric
public utility's CPRE Program guidelines then in effect as well as a pro forma
power purchase agreement used in its most recent CPRE RFP
Solicitation.
(3) Upon
the expiration of the CPRE Program Procurement Period, the electric public
utility shall file a CPRE Program Plan in the following calendar year
identifying any additional CPRE Program procurement requirements, as provided
for in G.S.
62-110.8(a).
(4) In any year in which an electric public
utility determines that it has fully complied with the CPRE Program
requirements set forth in
G.S.
62-110.8(a), the electric
public utility shall notify the Commission in its CPRE Program Plan, and may
petition the Commission to discontinue the CPRE Program Plan filing
requirements beginning in the subsequent calendar year.
(h) CPRE Program Compliance Report.
(1) Each electric public utility shall file
its annual CPRE Program compliance report, together with direct testimony and
exhibits of expert witnesses, on the same date that it files its application to
recover costs pursuant to subsection (j) of this rule. The Commission shall
consider each electric public utility's CPRE Program compliance report at the
hearing provided for in subsection (j) and shall determine whether the electric
public utility is in compliance with the CPRE Program requirements of
G.S.
62-110.8.
(2) Beginning in 2019, and each year
thereafter, each electric public utility shall file with the Commission a
report describing the electric public utility's competitive procurement of
renewable energy resources under its CPRE Program and ongoing actions to comply
with the requirements of
G.S.
62-110.8 during the previous calendar year,
which shall be the "reporting year." The report shall include the following
information, including supporting documentation:
(i) a description of CPRE RFP Solicitation(s)
undertaken by the electric public utility during the reporting year, including
an identification of each proposal eliminated pursuant to subsection (f)(3)(ii)
of this rule and an explanation of the utility's basis for elimination of each
proposal;
(ii) a description of the
sources, amounts, and costs of third-party power purchase agreements and
proposed authorized revenues for utility-owned assets for renewable energy
resources procured through CPRE RFP Solicitation(s) during the reporting year,
including the dates of all CPRE Program contracts or utility commitments to
procure renewable energy resources during the reporting year;
(iii) the forecasted nameplate capacity and
megawatt-hours of renewable energy and the number of renewable energy
certificates obtained through the CPRE Program during the reporting
year;
(iv) identification of all
proposed renewable energy facilities under development by the electric public
utility that were proposal into a CPRE RFP Solicitation during the reporting
year, including whether any non-publicly available transmission or distribution
system operations information was used in preparing the proposal, and, if so,
an explanation of how such information was made available to third parties that
notified the utility of their intention to submit a proposal in the same CPRE
RFP Solicitation;
(v) the electric
public utility's avoided cost rates applicable to the CPRE RFP Solicitation(s)
undertaken during the reporting year and confirmation that all renewable energy
resources procured through a CPRE RFP Solicitation are priced at or below the
electric public utility's avoided cost rates;
(vi) the actual total costs and authorized
revenues incurred by the electric public utility during the calendar year to
comply with
G.S.
62-110.8;
(vii) the status of the electric public
utility's compliance with the aggregate CPRE Program procurement requirements
set forth in
G.S.
62-110.8(a);
(viii) a copy of the contract then in effect
between the electric public utility and Independent Administrator, supporting
information regarding the administrative fees collected from participants in
the CPRE RFP Solicitation during the reporting year, as well as any cost
incurred by the electric public utility during the reporting year to implement
the CPRE RFP Solicitation; and
(ix)
certification by the Independent Administrator that all public utility and
third-party proposal responses were evaluated under the published CPRE Program
Methodology and that all proposals were treated equitably through the CPRE RFP
Solicitation(s) during the reporting year.
(i) Compliance with CPRE Program
Requirements.
(1) An electric public utility
shall be in compliance with the CPRE Program requirements during a given year
where the Commission determines that the electric public utility's CPRE Program
plan is reasonably designed to meet the requirements of
G.S.
62-110.8 and, based on the utility's most
recently filed CPRE Program compliance report, that the electric public utility
is reasonably and prudently implementing the CPRE Program
requirements.
(2) An electric
public utility, or other interested party, may petition the Commission to
modify or delay the provisions of
G.S.
62-110.8 in whole or in part. The Commission
shall allow a modification or delay upon finding that it is in the public
interest to do so.
(3) Renewable
energy certificates purchased or earned by an electric public utility while
complying with
G.S.
62-110.8 must have been earned after January
1, 2018, and may be retired to meet an electric public utility's REPS
compliance obligations under
G.S.
62-133.8.
(4) The owner of any renewable energy
facility included as part of a proposal selected through a CPRE RFP
Solicitation shall register the facility as a new renewable energy facility
under Rule R8-66 no later than 60 calendar days from receiving written
notification that the facility was included as part of a proposal selected and
shall participate in the North Carolina Renewable Energy Tracking System
(NC-RETS) to facilitate the issuance or importation of renewable energy
certificates contracted for under the CPRE Program.
(j) Cost or authorized revenue recovery.
(1) Beginning in 2018, for each electric
public utility, the Commission shall schedule an annual public hearing pursuant
to G.S.
62-110.8(g) to review the
costs incurred or anticipated to be incurred by the electric public utility to
comply with
G.S.
62-110.8. The annual rider hearing for each
electric public utility will be scheduled as soon as practicable after the
hearing held by the Commission for the electric public utility under Rule
R8-55.
(2) The Commission shall
permit each electric public utility to charge an increment or decrement as a
rider to its rates to recover in a timely manner the reasonable and prudent
costs incurred and anticipated to be incurred to implement its CPRE Program and
to comply with
G.S.
62-110.8. In any application for cost
recovery and collection of authorized revenues wherein the utility proposes to
recover costs or collect revenues attributable to a utility-owned renewable
energy facility calculated on a market basis, in lieu of a cost-of-service
basis, the utility shall support its application with testimony specifically
addressing the calculation of those costs and revenues sufficient to
demonstrate that recovery on a market basis is in the public
interest.
(3) Unless otherwise
ordered by the Commission, the test period for each electric public utility
shall be the same as its test period for purposes of Rule R8-55.
(4) Rates set pursuant to this section shall
be recovered during a fixed recovery period that shall coincide, to the extent
practical, with the recovery period for the cost of fuel and fuel-related cost
rider established pursuant to Rule R8-55.
(5) The costs and authorized revenue will be
further modified through the use of a CPRE Program experience modification
factor (CPRE EMF) rider. The CPRE EMF rider will reflect the difference between
reasonable and prudently-incurred CPRE Program projected costs, authorized
revenue, and the revenues that were actually realized during the test period
under the CPRE Program rider then in effect. Upon request of the electric
public utility, the Commission shall also incorporate in this determination the
experienced over-recovery or under-recovery of the costs and authorized revenue
up to 30 days prior to the date of the hearing, provided that the
reasonableness and prudence of these costs and authorized revenues shall be
subject to review in the utility's next annual CPRE Program cost recovery
hearing.
(6) The CPRE EMF rider
will remain in effect for a fixed 12-month period following establishment and
will carry through as a rider to rates established in any intervening general
rate case proceedings.
(7) Pursuant
to G.S.
62-130(e), any
over-collection of reasonably and prudently-incurred costs and authorized
revenues to be refunded to an electric public utility's customers through
operation of the CPRE EMF rider shall include an amount of interest, at such
rate as the Commission determines to be just and reasonable, not to exceed the
maximum statutory rate.
(8) Each
electric public utility shall follow deferred accounting with respect to the
difference between actual reasonably and prudently-incurred costs or authorized
revenue and related revenues realized under rates in effect.
(9) The annual increase in the aggregate
amount of costs recovered under
G.S.
62-110.8(g) in any recovery
period from its North Carolina retail customers shall not exceed one percent
(1%) of the electric public utility's total North Carolina retail
jurisdictional gross revenues for the preceding calendar year determined as of
December 31 of the previous calendar year. Any amount in excess of that limit
shall be carried over and recovered in the next recovery period when the annual
increase in the aggregate amount of costs to be recovered is less than one
percent (1%).
(10) Each electric
public utility, at a minimum, shall submit to the Commission for purposes of
investigation and hearing the information required for the CPRE Program
compliance report for the 12-month test period established in subsection (3)
consistent with Rule R8-55, accompanied by supporting workpapers and direct
testimony and exhibits of expert witnesses, and any change in rates proposed by
the electric public utility at the same time that it files the information
required by Rule R8-55.
(11) The
electric public utility shall publish a notice of the annual hearing for 2
successive weeks in a newspaper or newspapers having general circulation in its
service area, normally beginning at least 30 days prior to the hearing,
notifying the public of the hearing before the Commission pursuant to
G.S.
62-110.8(g) and setting
forth the time and place of the hearing.
(12) Persons having an interest in said
hearing may file a petition to intervene setting forth such interest at least
15 days prior to the date of the hearing. Petitions to intervene filed less
than 15 days prior to the date of the hearing may be allowed at the discretion
of the Commission for good cause shown.
(13) The Public Staff and intervenors shall
file direct testimony and exhibits of expert witnesses at least 15 days prior
to the hearing date. If a petition to intervene is filed less than 15 days
prior to the hearing date, it shall be accompanied by any direct testimony and
exhibits of expert witnesses the intervenor intends to offer at the
hearing.
(14) The electric public
utility may file rebuttal testimony and exhibits of expert witnesses no later
than 5 days prior to the hearing date.
(15) The burden of proof as to whether CPRE
Program-related costs or authorized revenues to be recovered under this section
were reasonable and prudently-incurred shall be on the electric public
utility.
(k) Expedited
review and approval of Certificate of Public Convenience and Necessity for
renewable energy facilities owned by an electric public utility and procured
under the CPRE Program.
(1) Scope of Section.
(i) This section applies to applications for
a certificate of public convenience and necessity pursuant to
G.S.
62-110.8(h)(3) filed by an
electric public utility for the construction and operation of renewable energy
facilities owned by an electric public utility for compliance with the
requirements of
G.S.
62-110.8, and to petitions to transfer a
certificate of public convenience and necessity to an electric public utility
for compliance with the requirements of
G.S.
62-110.8. Applications and petitions filed
pursuant to this subsection shall be required to comply with the requirements
of this subsection and shall not otherwise be required to comply with the
requirements of
G.S.
62-82 or
62-110.1, or Commission Rules
R8-61 or R8-64.
(ii) The
construction of a renewable energy facility for the generation of electricity
shall include not only the building of a new building, structure or generator,
but also the renovation or reworking of an existing building, structure or
generator in order to enable it to operate as a generating facility.
(iii) This section shall apply to any person
within its scope who begins construction of a renewable energy facility without
first obtaining a certificate of public convenience and necessity. In such
circumstances, the application shall include an explanation for the applicant's
beginning of construction before the obtaining of the certificate.
(iv) This section applies to a petition to
transfer an existing certificate of public convenience and necessity issued for
renewable energy facilities that an electric public utility acquires from a
third party with the intent to own and operate the renewable energy facility to
comply with the requirements of
G.S.
62-110.8.
(2) The Application. The application shall be
comprised of the following exhibits:
(i)
Exhibit 1 shall contain:
1. The full and
correct name, business address, business telephone number, and electronic
mailing address of the electric public utility;
2. A statement describing the electric public
utility's corporate structure and affiliation with any other electric public
utility, if any; and
3. The
ownership of the facility site and, if the owner is other than the applicant,
the applicant's interest in the facility site.
(ii) Exhibit 2 shall contain the following
site information:
1. A color map or aerial
photo showing the location of the generating facility site in relation to local
highways, streets, rivers, streams, and other generally known local landmarks,
with the proposed location of major equipment indicated on the map or photo,
including: the generator, fuel handling equipment, plant distribution system,
startup equipment, site boundary, planned and existing pipelines, planned and
existing roads, planned and existing water supplies, and planned and existing
electric facilities. A U.S. Geological Survey map or an aerial photo map
prepared via the State's geographic information system is preferred;
2. The E911 street address, county in which
the proposed facility would be located, and GPS coordinates of the approximate
center of the proposed facility site to the nearest second or one thousandth of
a degree; and
3. Whether the
electric public utility is the site owner, and, if not, providing the full and
correct name of the site owner and the electric public utility's interest in
the site.
(iii) Exhibit
3 shall include:
1. The nature of the
renewable energy facility, including the type and source of its power or
fuel;
2. A description of the
buildings, structures and equipment comprising the renewable energy facility
and the manner of its operation;
3.
The gross and net projected maximum dependable capacity of the renewable energy
facility as well as the renewable energy facility's nameplate capacity,
expressed as megawatts (alternating current);
4. The projected date on which the renewable
energy facility will come on line;
5. The service life of the project;
6. The projected annual hourly production
profile for the first full year of operation of the renewable energy facility
in kilowatt-hours, including an explanation of potential factors influencing
the shape of the production profile, including the following, if applicable:
fixed tilt or tracking panel arrays, inverter loading ratio, over-paneling,
clipped energy, or inverter AC output power limits;
7. The projected annual production of
renewable energy certificates that is eligible for compliance with the State's
renewable energy and energy efficiency portfolio standard.
(iv) Exhibit 3 shall include:
1. A complete list of all federal and state
licenses, permits and exemptions required for construction and operation of the
renewable energy facility and a statement of whether each has been obtained or
applied for; and
2. A copy of those
that have been obtained should be filed with the application; a copy of those
that have not been obtained at the time of the application should be filed with
the Commission as soon as they are obtained.
(v) Exhibit 4 shall contain the expected cost
to construct, operate and maintain the proposed facility.
(vi) Exhibit 5 shall contain the following
resource planning information:
1. The
utility's most recent biennial report and the most recent annual report filed
pursuant to Rule R8-60, plus any proposals by the utility to update said
reports;
2. The extent to which the
proposed facility would conform to the utility's most recent biennial report
and the most recent annual report that was filed pursuant to Rule
R8-60;
3. A statement of how the
facility would contribute to resource and fuel diversity, whether the facility
would have dual-fuel capability, and how much fuel would be stored at the
site;
4. An explanation of the need
for the facility, including information on energy and capacity forecasts;
and
5. An explanation of how the
proposed facility meets the identified energy and capacity needs, including the
anticipated facility capacity factor, heat rate, and service life.
(3) Petition for
transfer of certificate of public convenience and necessity. When an electric
public utility procures an operating renewable energy facility through a CPRE
RFP Solicitation with intent to own and operate the facility and the renewable
energy facility has been previously issued a certificate of public convenience
and necessity, the electric public utility shall petition the Commission to
transfer the certificate of public convenience and necessity. A petition
requesting that the Commission transfer a certificate of public convenience and
necessity shall include the following:
(i) a
description of the terms and conditions of the electric public utility's
procurement of the renewable energy facility under the CPRE Program and an
identification of any significant changes to the information in the application
for the certificate of public convenience and necessity, which the Commission
considered in the issuance of the certificate for that facility;
(ii) The signature and verification of the
electric public utility's employee or agent responsible for preparing the
petition stating that the contents thereof are known to the employee or agent
and are accurate to the best of that person's knowledge; and
(iii) The verification of a person authorized
to act on behalf of the certificate holder that it intends to transfer the
certificate of public convenience and necessity to the electric public
utility.
(4) Procedure
for Acquiring Project Development Assets. - When an electric public utility
purchases from a third party developer assets that include the rights to
construct and operate a renewable energy facility that has been issued a
certificate of public convenience and necessity with the intent of further
developing the project and submitting the renewable energy facility in to a
future CPRE RFP Solicitation, the electric public utility shall provide notice
to the Commission in the docket where the certificate of public convenience and
necessity was issued that the electric public utility has acquired ownership of
the project development assets. The electric public utility shall not be
required to submit a petition for transfer of the certificate of public
convenience and necessity unless and until the project is selected through a
CPRE RFP Solicitation or the electric public utility otherwise elects to
proceed with construction of the renewable energy facility. If the project is
selected through a CPRE RFP Solicitation or the electric public utility
otherwise elects to proceed with construction of the renewable energy facility,
the electric public utility shall file a petition to transfer the certificate
of public convenience and necessity, and the Commission shall process the
petition in the same manner provided in (6) of this subsection. In any event,
the petition shall be filed prior to the electric public utility commencing the
construction or operation of the renewable energy facility, and no rights under
the certificate of public convenience and necessity shall transfer to the
electric public utility unless and until the Commission approves transfer of
the certificate.
(5) Procedure for
expedited review of applications for a certificate of public convenience and
necessity. - The Commission will process applications for certificates of
public convenience and necessity filed pursuant to this section as follows:
(i) The electric public utility shall file
with the Commission its preliminary plans at least 30 days before filing an
application for a certificate of public convenience and necessity. The
preliminary plans shall include the following:
1. Exhibit 1 shall contain the following site
information:
a. A color map or aerial photo (a
U.S. Geological Survey map or an aerial photo map prepared via the State's
geographic information system is preferred) showing the proposed site boundary
and layout, with all major equipment, including the generator and inverters,
planned and existing roads, planned and existing water supplies, and planned
and existing electric facilities;
b. The E911 street address, county in which
the proposed facility would be located, and GPS coordinates of the approximate
center of the proposed facility site to the nearest second or one thousandth of
a degree;
c. The full and correct
name of the site owner and, if the owner is other than the applicant, the
applicant's interest in the site;
d. A brief general description of practicable
transmission line routes emanating from the site, including a color map showing
their general location; and
e. The
gross, net, and nameplate generating capacity of each unit and the entire
facility's total projected dependable capacity in alternating current
(AC).
2. Exhibit 2 shall
contain a list of all agencies from which approvals will be sought covering
various aspects of any generation facility constructed on the site and the
title and nature of such approvals; and
3. Exhibit 3 shall include a schedule showing
the anticipated beginning dates for construction, testing, and commercial
operation of the generating facility.
(ii) Within ten days of the filing of its
preliminary plans, the Applicant shall cause to be published a notice of its
filing of preliminary plans to apply for an expedited certificate of public
convenience and necessity in a newspaper having general circulation in the area
where the generating facility. The notice shall be in the form provided in the
Appendix to this Chapter, and the applicant shall be responsible for filing
with the Commission an affidavit of publication to the effect that the notice
was published as required by this rule;
(iii) The Chief Clerk will deliver 2 copies
of the electric public utility's preliminary plans to the Clearinghouse
Coordinator of the Office of Policy and Planning of the Department of
Administration for distribution by the Coordinator to State agencies having an
interest in the application. The Chief Clerk will request comments from state
agencies within 30 days of delivering notice to the Clearinghouse
Coordinator.
(iv) The applicant
shall file the application within 60 days of filing of its preliminary
plans.
(v) The Commission will
issue an order requesting the Public Staff to investigate the application and
present its findings, conclusions, and recommendations at the Regular
Commission Staff Conference to be held on the third Monday following the filing
of the application, and requiring the applicant to publish notice of the
application and of the time and place of the Staff Conference where the
application will be considered. The notice shall be published once in a
newspaper of general circulation in the area where the generating facility is
proposed to be constructed. The applicant shall be responsible for filing with
the Commission an affidavit of publication to the effect that the notice was
published as required by this rule.
(vi) If significant complaint(s) are filed
with the Commission prior to the Regular Commission Staff Conference where the
application is to be considered, the Public Staff shall report the same to the
Commission and the Commission shall schedule a public hearing to determine
whether a certificate should be awarded. The Commission will give reasonable
notice of the time and place of the hearing to the applicant and to each
complaining party, and require the applicant to publish notice of the time and
place of the hearing. The notice shall be published once in a newspaper of
general circulation in the area where the generating facility is proposed to be
constructed. The applicant shall be responsible for filing with the Commission
an affidavit of publication to the effect that the notice was published as
required by this rule.
(vii) If no
significant complaint(s) are received within the time specified, the Commission
may, upon its own initiative, order and schedule a hearing to determine whether
a certificate should be awarded. The Commission will give reasonable notice of
the time and place of the hearing to the applicant and require the applicant to
publish notice of the time and place of the hearing. The notice shall be
published once in a newspaper of general circulation in the area where the
generating facility is proposed to be constructed. The applicant shall be
responsible for filing with the Commission an affidavit of publication to the
effect that the notice was published as required by this rule.
(viii) The Commission, for good cause shown,
may order such additional investigation, further hearings, and required filings
as it deems necessary and appropriate to address the issues raised in the
application or by parties opposing the issuance of the requested certificate;
and
(ix) If no significant
complaint(s) are filed with the Commission and the Commission does not order a
hearing on its own initiative nor order additional investigation, further
hearings, or required filings, then the Commission shall consider the
application at the Regular Commission Staff Conference as scheduled and,
thereafter, issue an order on the application within 30 days after the
application is filed, or as near after the 30th days
as reasonably practicable. Where the Commission deems issuance of an order on
the application within 30 days is impossible, the Commission may issue a notice
of decision within 30 days after the application is filed and subsequently
issue a final order in the matter.
(6) Procedure for Expedited Transfer of
certificate of public convenience and necessity. - The Commission shall process
a petition to transfer a certificate of public convenience pursuant to the CPRE
Program as follows:
(i) Any petition to
transfer an existing certificate of public convenience and necessity shall be
signed and verified by the electric public utility applicant. A petition to
transfer an existing certificate of public convenience and necessity shall also
be verified by the entity which was initially granted the certificate of public
convenience and necessity that it intends to transfer the certificate of public
convenience and necessity to the electric public utility.
(ii) The Commission will issue an order
requesting the Public Staff to investigate the petition and present its
findings, conclusions, and recommendations at the Regular Commission Staff
Conference to be held on the third Monday following the filing of the
application, and requiring the applicant to publish notice of the petition and
of the time and place of the Staff Conference where the application will be
considered. The notice shall be published once in a newspaper of general
circulation in the area where the generating facility is located. The applicant
shall be responsible for filing with the Commission an affidavit of publication
to the effect that the notice was published as required by this rule.
(iii) If significant complaint(s) are filed
with the Commission prior to the Regular Commission Staff Conference where the
petition is to be considered, the Public Staff shall report the same to the
Commission and the Commission shall schedule a public hearing to determine
whether the petition for transfer of the certificate should be granted. The
Commission will give reasonable notice of the time and place of the hearing to
the applicant and to each complaining party, and require the applicant to
publish notice of the time and place of the hearing. The notice shall be
published once in a newspaper of general circulation in the area where the
generating facility is located. The applicant shall be responsible for filing
with the Commission an affidavit of publication to the effect that the notice
was published as required by this rule.
(iv) If no significant complaint(s) are
received within the time specified, the Commission may, upon its own
initiative, order and schedule a hearing to determine whether a certificate
should be awarded. The Commission will give reasonable notice of the time and
place of the hearing to the applicant and require the applicant to publish
notice of the time and place of the hearing. The notice shall be published once
in a newspaper of general circulation in the area where the generating facility
is located. The applicant shall be responsible for filing with the Commission
an affidavit of publication to the effect that the notice was published as
required by this rule.
(v) The
Commission, for good cause shown, may order such additional investigation,
further hearings, and required filings as it deems necessary and appropriate to
address the issues raised in the application or by parties opposing the
issuance of the requested certificate; and
(vi) If no significant complaint(s) are filed
with the Commission and the Commission does not order a hearing on its own
initiative nor order additional investigation, further hearings, or required
filings, then the Commission shall consider the petition at the Regular
Commission Staff Conference as scheduled and, thereafter, issue an order on the
application within 30 days after the application is filed, or as near after the
30th days as reasonably practicable. Where the
Commission deems issuance of an order on the application within 30 days is
impossible, the Commission may issue a notice of decision within 30 days after
the application is filed and subsequently issue a final order in the
matter.
(l)
CPRE Program Power Purchase Agreement Requirements
(1) Prior to holding a CPRE RFP Solicitation,
and on or before the date set by Commission order, the Independent
Administrator shall post the pro forma contract to be utilized during the CPRE
RFP Solicitation on the IA Website to inform market participants of terms and
conditions of the competitive solicitation. The electric public utility shall
also file the pro forma contract with the Commission and identify any material
changes to the pro forma contract terms and conditions from the contract used
in the electric public utility's most recent CPRE RFP Solicitation.
(2) Each electric public utility shall
include appropriate language in all pro forma contracts (i) providing the
procuring electric public utility rights to dispatch, operate, and control the
solicited renewable energy facilities in the same manner as the utility's own
generating resources; (ii) defining limits and compensation for resource
dispatch and curtailments; (iii) defining environmental and renewable energy
attributes to include all attributes that would be created by renewable energy
facilities owned by the electric public utility; and (iv) prohibiting the
seller from claiming or otherwise remarketing the environmental and renewable
energy attributes, including the renewable energy certificates being procured
by the electric public utility under power purchase agreements entered into
under the CPRE Program. An electric public utility may propose redefining its
rights to dispatch, operate, and control solicited renewable energy facilities,
including defining limits and compensation for resource dispatch and
curtailments, in pro forma contracts to be offered in future CPRE RFP
Solicitations. In addition, an electric public utility may, within a single
CPRE RFP Solicitation, propose multiple pro forma contracts that offer
different rights to dispatch, operate, and control renewable energy
facilities.
(3) No later than 30
days after an electric public utility executes a power purchase agreement
pursuant to a CPRE RFP Solicitation, the public utility shall file the power
purchase agreement with the Commission. If the power purchase agreement is with
an Affiliate, the electric public utility shall file the power purchase
agreement with the Commission pursuant to
G.S.
62-153(a).
(4) Upon expiration of the term of a power
purchase agreement procured pursuant to a CPRE RFP Solicitation, a renewable
energy facility owner, other than the electric public utility, may enter into a
new contract with the electric public utility pursuant to
G.S.
62-156 or obtain a new contract based on an
updated market based mechanism, as determined by the Commission pursuant to
G.S.
62-110.8(a). If market-based
authorized revenue for a generating facility owned by the electric public
utility and procured pursuant to this Rule was initially determined by the
Commission to be in the public interest, then the electric public utility shall
similarly be permitted to continue to receive authorized revenue based on an
updated market based mechanism, as determined by the Commission pursuant to
G.S.
62-110.8(a). Any market
based rate for either utility owned or non-utility owned facilities shall not
exceed the electric public utility's avoided cost rate established pursuant to
G.S.
62-156. If the electric public utility's
initial proposal includes assumptions about pricing after the initial term,
such information shall be made available to the Independent Administrator and
all participants.
NCUC Docket No. E-100,
Sub 150, 11/06/2017; NCUC Docket No. E-100, Sub 150, 04/09/2018; NCUC Docket
No. E-100, Sub 166, 08/31/2020.